Title 49
PART 195 SUBPART C
Subpart C - Design Requirements
- 30 U.S.C. 185(w)(3), 49 U.S.C. 5103, 60101 et seq., and 49 CFR 1.97.
- Amdt. 195-22, 46 FR 38360, July 27, 1981, unless otherwise noted.
49:3.1.1.2.11.3.20.1 | SECTION 195.100 | 195.100 Scope. | |
49:3.1.1.2.11.3.20.2 | SECTION 195.101 | 195.101 Qualifying metallic components other than pipe. | |
49:3.1.1.2.11.3.20.3 | SECTION 195.102 | 195.102 Design temperature. | |
49:3.1.1.2.11.3.20.4 | SECTION 195.104 | 195.104 Variations in pressure. | |
49:3.1.1.2.11.3.20.5 | SECTION 195.106 | 195.106 Internal design pressure. | |
49:3.1.1.2.11.3.20.6 | SECTION 195.108 | 195.108 External pressure. | |
49:3.1.1.2.11.3.20.7 | SECTION 195.110 | 195.110 External loads. | |
49:3.1.1.2.11.3.20.8 | SECTION 195.111 | 195.111 Fracture propagation. | |
49:3.1.1.2.11.3.20.9 | SECTION 195.112 | 195.112 New pipe. | |
49:3.1.1.2.11.3.20.10 | SECTION 195.114 | 195.114 Used pipe. | |
49:3.1.1.2.11.3.20.11 | SECTION 195.116 | 195.116 Valves. | |
49:3.1.1.2.11.3.20.12 | SECTION 195.118 | 195.118 Fittings. | |
49:3.1.1.2.11.3.20.13 | SECTION 195.120 | 195.120 Passage of internal inspection devices. | |
49:3.1.1.2.11.3.20.14 | SECTION 195.122 | 195.122 Fabricated branch connections. | |
49:3.1.1.2.11.3.20.15 | SECTION 195.124 | 195.124 Closures. | |
49:3.1.1.2.11.3.20.16 | SECTION 195.126 | 195.126 Flange connection. | |
49:3.1.1.2.11.3.20.17 | SECTION 195.128 | 195.128 Station piping. | |
49:3.1.1.2.11.3.20.18 | SECTION 195.130 | 195.130 Fabricated assemblies. | |
49:3.1.1.2.11.3.20.19 | SECTION 195.132 | 195.132 Design and construction of aboveground breakout tanks. | |
49:3.1.1.2.11.3.20.20 | SECTION 195.134 | 195.134 Leak detection. |