Appendix F to Part 192 - Criteria for Conducting Integrity Assessments Using Guided Wave Ultrasonic Testing (GWUT)
49:3.1.1.2.8.18.8.1.19 : Appendix F
Appendix F to Part 192 - Criteria for Conducting Integrity
Assessments Using Guided Wave Ultrasonic Testing (GWUT)
This appendix defines criteria which must be properly
implemented for use of guided wave ultrasonic testing (GWUT) as an
integrity assessment method. Any application of GWUT that does not
conform to these criteria is considered “other technology” as
described by §§ 192.710(c)(7), 192.921(a)(7), and 192.937(c)(7),
for which OPS must be notified 90 days prior to use in accordance
with §§ 192.921(a)(7) or 192.937(c)(7). GWUT in the “Go-No Go” mode
means that all indications (wall loss anomalies) above the testing
threshold (a maximum of 5% of cross sectional area (CSA)
sensitivity) be directly examined, in-line tool inspected, pressure
tested, or replaced prior to completing the integrity assessment on
the carrier pipe.
I. Equipment and Software: Generation. The equipment and
the computer software used are critical to the success of the
inspection. Computer software for the inspection equipment must be
reviewed and updated, as required, on an annual basis, with
intervals not to exceed 15 months, to support sensors, enhance
functionality, and resolve any technical or operational issues
identified.
II. Inspection Range. The inspection range and
sensitivity are set by the signal to noise (S/N) ratio but must
still keep the maximum threshold sensitivity at 5% cross sectional
area (CSA). A signal that has an amplitude that is at least twice
the noise level can be reliably interpreted. The greater the S/N
ratio the easier it is to identify and interpret signals from small
changes. The signal to noise ratio is dependent on several
variables such as surface roughness, coating, coating condition,
associated pipe fittings (T's, elbows, flanges), soil compaction,
and environment. Each of these affects the propagation of sound
waves and influences the range of the test. It may be necessary to
inspect from both ends of the pipeline segment to achieve a full
inspection. In general, the inspection range can approach 60 to 100
feet for a 5% CSA, depending on field conditions.
III. Complete Pipe Inspection. To ensure that the entire
pipeline segment is assessed there should be at least a 2 to 1
signal to noise ratio across the entire pipeline segment that is
inspected. This may require multiple GWUT shots. Double-ended
inspections are expected. These two inspections are to be overlaid
to show the minimum 2 to 1 S/N ratio is met in the middle. If
possible, show the same near or midpoint feature from both sides
and show an approximate 5% distance overlap.
IV. Sensitivity. The detection sensitivity threshold
determines the ability to identify a cross sectional change. The
maximum threshold sensitivity cannot be greater than 5% of the
cross sectional area (CSA).
The locations and estimated CSA of all metal loss features in
excess of the detection threshold must be determined and
documented.
All defect indications in the “Go-No Go” mode above the 5%
testing threshold must be directly examined, in-line inspected,
pressure tested, or replaced prior to completing the integrity
assessment.
V. Wave Frequency. Because a single wave frequency may
not detect certain defects, a minimum of three frequencies must be
run for each inspection to determine the best frequency for
characterizing indications. The frequencies used for the
inspections must be documented and must be in the range specified
by the manufacturer of the equipment.
VI. Signal or Wave Type: Torsional and Longitudinal. Both
torsional and longitudinal waves must be used and use must be
documented.
VII. Distance Amplitude Correction (DAC) Curve and Weld
Calibration. The distance amplitude correction curve accounts
for coating, pipe diameter, pipe wall and environmental conditions
at the assessment location. The DAC curve must be set for each
inspection as part of establishing the effective range of a GWUT
inspection. DAC curves provide a means for evaluating the
cross-sectional area change of reflections at various distances in
the test range by assessing signal to noise ratio. A DAC curve is a
means of taking apparent attenuation into account along the time
base of a test signal. It is a line of equal sensitivity along the
trace which allows the amplitudes of signals at different axial
distances from the collar to be compared.
VIII. Dead Zone. The dead zone is the area adjacent to
the collar in which the transmitted signal blinds the received
signal, making it impossible to obtain reliable results. Because
the entire line must be inspected, inspection procedures must
account for the dead zone by requiring the movement of the collar
for additional inspections. An alternate method of obtaining valid
readings in the dead zone is to use B-scan ultrasonic equipment and
visual examination of the external surface. The length of the dead
zone and the near field for each inspection must be documented.
IX. Near Field Effects. The near field is the region
beyond the dead zone where the receiving amplifiers are increasing
in power, before the wave is properly established. Because the
entire line must be inspected, inspection procedures must account
for the near field by requiring the movement of the collar for
additional inspections. An alternate method of obtaining valid
readings in the near field is to use B-scan ultrasonic equipment
and visual examination of the external surface. The length of the
dead zone and the near field for each inspection must be
documented.
X. Coating Type. Coatings can have the effect of
attenuating the signal. Their thickness and condition are the
primary factors that affect the rate of signal attenuation. Due to
their variability, coatings make it difficult to predict the
effective inspection distance. Several coating types may affect the
GWUT results to the point that they may reduce the expected
inspection distance. For example, concrete coated pipe may be
problematic when well bonded due to the attenuation effects. If an
inspection is done and the required sensitivity is not achieved for
the entire length of the pipe, then another type of assessment
method must be utilized.
XI. End Seal. When assessing cased carrier pipe with
GWUT, operators must remove the end seal from the casing at each
GWUT test location to facilitate visual inspection. Operators must
remove debris and water from the casing at the end seals. Any
corrosion material observed must be removed, collected and reviewed
by the operator's corrosion technician. The end seal does not
interfere with the accuracy of the GWUT inspection but may have a
dampening effect on the range.
XII. Weld Calibration to set DAC Curve. Accessible welds,
along or outside the pipeline segment to be inspected, must be used
to set the DAC curve. A weld or welds in the access hole (secondary
area) may be used if welds along the pipeline segment are not
accessible. In order to use these welds in the secondary area,
sufficient distance must be allowed to account for the dead zone
and near field. There must not be a weld between the transducer
collar and the calibration weld. A conservative estimate of the
predicted amplitude for the weld is 25% CSA (cross sectional area)
and can be used if welds are not accessible. Calibrations (setting
of the DAC curve) should be on pipe with similar properties such as
wall thickness and coating. If the actual weld cap height is
different from the assumed weld cap height, the estimated CSA may
be inaccurate and adjustments to the DAC curve may be required.
Alternative means of calibration can be used if justified by a
documented engineering analysis and evaluation.
XIII. Validation of Operator Training. Pipeline operators
must require all guided wave service providers to have
equipment-specific training and experience for all GWUT Equipment
Operators which includes training for:
A. Equipment operation,
B. field data collection, and
C. data interpretation on cased and buried pipe.
Only individuals who have been qualified by the manufacturer or
an independently assessed evaluation procedure similar to ISO 9712
(Sections: 5 Responsibilities; 6 Levels of Qualification; 7
Eligibility; and 10 Certification), as specified above, may operate
the equipment. A senior-level GWUT equipment operator with pipeline
specific experience must provide onsite oversight of the inspection
and approve the final reports. A senior-level GWUT equipment
operator must have additional training and experience, including
training specific to cased and buried pipe, with a quality control
program which that conforms to Section 12 of ASME B31.8S (for
availability, see § 192.7).
XIV. Training and Experience Minimums for Senior Level GWUT
Equipment Operators:
• Equipment Manufacturer's minimum qualification for equipment
operation and data collection with specific endorsements for
casings and buried pipe
• Training, qualification and experience in testing procedures
and frequency determination
• Training, qualification and experience in conversion of guided
wave data into pipe features and estimated metal loss (estimated
cross-sectional area loss and circumferential extent)
• Equipment Manufacturer's minimum qualification with specific
endorsements for data interpretation of anomaly features for pipe
within casings and buried pipe.
XV. Equipment: Traceable from vendor to inspection
company. An operator must maintain documentation of the version
of the GWUT software used and the serial number of the other
equipment such as collars, cables, etc., in the report.
XVI. Calibration Onsite. The GWUT equipment must be
calibrated for performance in accordance with the manufacturer's
requirements and specifications, including the frequency of
calibrations. A diagnostic check and system check must be performed
on-site each time the equipment is relocated to a different casing
or pipeline segment. If on-site diagnostics show a discrepancy with
the manufacturer's requirements and specifications, testing must
cease until the equipment can be restored to manufacturer's
specifications.
XVII. Use on Shorted Casings (direct or electrolytic).
GWUT may not be used to assess shorted casings. GWUT operators must
have operations and maintenance procedures (see § 192.605)
to address the effect of shorted casings on the GWUT signal. The
equipment operator must clear any evidence of interference, other
than some slight dampening of the GWUT signal from the shorted
casing, according to their operating and maintenance procedures.
All shorted casings found while conducting GWUT inspections must be
addressed by the operator's standard operating procedures.
XVIII. Direct examination of all indications above the
detection sensitivity threshold. The use of GWUT in the “Go-No
Go” mode requires that all indications (wall loss anomalies) above
the testing threshold (5% of CSA sensitivity) be directly examined
(or replaced) prior to completing the integrity assessment on the
cased carrier pipe or other GWUT application. If this cannot be
accomplished, then alternative methods of assessment (such as
hydrostatic pressure tests or ILI) must be utilized.
XIV. Timing of direct examination of all indications above
the detection sensitivity threshold. Operators must either
replace or conduct direct examinations of all indications
identified above the detection sensitivity threshold according to
the table below. Operators must conduct leak surveys and reduce
operating pressure as specified until the pipe is replaced or
direct examinations are completed.
Required Response to GWUT Indications
GWUT criterion |
Operating pressure less than
or equal to 30% SMYS |
Operating pressure over 30
and less than or equal to 50% SMYS |
Operating pressure over 50%
SMYS |
Over the detection
sensitivity threshold (maximum of 5% CSA) |
Replace or direct examination
within 12 months, and instrumented leak survey once every 30
calendar days |
Replace or direct examination
within 6 months, instrumented leak survey once every 30 calendar
days, and maintain MAOP below the operating pressure at time of
discovery |
Replace or direct examination
within 6 months, instrumented leak survey once every 30 calendar
days, and reduce MAOP to 80% of operating pressure at time of
discovery. |
[Amdt. No. 192-125, 84 FR 52255, Oct. 1, 2019]