Title 30

SECTION 585.600

585.600 What plans and information must I submit to BOEM before I conduct activities on my lease or grant

§ 585.600 What plans and information must I submit to BOEM before I conduct activities on my lease or grant?

You must submit a SAP, COP, or GAP and receive BOEM approval as set forth in the following table:

Before you: you must:
(a) conduct any site assessment activities on your commercial lease, submit and obtain approval for your SAP according to §§ 585.605 through 585.613.
(b) conduct any activities pertaining to construction of facilities for commercial operations on your commercial lease, submit and obtain approval for your COP, according to §§ 585.620 through 585.629.
(c) conduct any activities on your limited lease, ROW grant, or RUE grant in any OCS area, submit and obtain approval for your GAP according to §§ 585.640 through 585.648.