Title 30

PART 585 SUBPART I

Subpart I - Decommissioning

30:2.0.3.5.13.9.314SUBJGRP 314
Decommissioning Obligations and Requirements
30:2.0.3.5.13.9.314.1SECTION 585.900
   585.900 Who must meet the decommissioning obligations in this subpart
30:2.0.3.5.13.9.314.2SECTION 585.901
   585.901 When do I accrue decommissioning obligations
30:2.0.3.5.13.9.314.3SECTION 585.902
   585.902 What are the general requirements for decommissioning for facilities authorized under my SAP, COP, or GAP
30:2.0.3.5.13.9.314.4SECTION 585.903
   585.903 What are the requirements for decommissioning FERC-licensed hydrokinetic facilities
30:2.0.3.5.13.9.314.5SECTION 585.904
   585.904 Can I request a departure from the decommissioning requirements
30:2.0.3.5.13.9.315SUBJGRP 315
Decommissioning Applications
30:2.0.3.5.13.9.315.6SECTION 585.905
   585.905 When must I submit my decommissioning application
30:2.0.3.5.13.9.315.7SECTION 585.906
   585.906 What must my decommissioning application include
30:2.0.3.5.13.9.315.8SECTION 585.907
   585.907 How will BOEM process my decommissioning application
30:2.0.3.5.13.9.315.9SECTION 585.908
   585.908 What must I include in my decommissioning notice
30:2.0.3.5.13.9.316SUBJGRP 316
Facility Removal
30:2.0.3.5.13.9.316.10SECTION 585.909
   585.909 When may BOEM authorize facilities to remain in place following termination of a lease or grant
30:2.0.3.5.13.9.316.11SECTION 585.910
   585.910 What must I do when I remove my facility
30:2.0.3.5.13.9.316.12SECTION 585.911
   585.911 [Reserved]
30:2.0.3.5.13.9.317SUBJGRP 317
Decommissioning Report
30:2.0.3.5.13.9.317.13SECTION 585.912
   585.912 After I remove a facility, cable, or pipeline, what information must I submit
30:2.0.3.5.13.9.318SUBJGRP 318
Compliance With an Approved Decommissioning Application
30:2.0.3.5.13.9.318.14SECTION 585.913
   585.913 What happens if I fail to comply with my approved decommissioning application