Title 30

SECTION 585.912

585.912 After I remove a facility, cable, or pipeline, what information must I submit

§ 585.912 After I remove a facility, cable, or pipeline, what information must I submit?

Within 60 days after you remove a facility, cable, or pipeline, you must submit a written report to BOEM that includes the following:

(a) A summary of the removal activities, including the date they were completed;

(b) A description of any mitigation measures you took; and

(c) If you used explosives, a statement signed by your authorized representative that certifies that the types and amount of explosives you used in removing the facility were consistent with those in the approved decommissioning application.