Appendix C to Part 222 - Guide to Establishing Quiet Zones
49:4.1.1.1.17.5.15.1.27 : Appendix C
Appendix C to Part 222 - Guide to Establishing Quiet Zones
Introduction
This Guide to Establishing Quiet Zones (Guide) is divided into
five sections in order to address the variety of methods and
conditions that affect the establishment of quiet zones under this
rule.
Section I of the Guide provides an overview of the different
ways in which a quiet zone may be established under this rule. This
includes a brief discussion on the safety thresholds that must be
attained in order for train horns to be silenced and the relative
merits of each. It also includes the two general methods that may
be used to reduce risk in the proposed quiet zone, and the
different impacts that the methods have on the quiet zone
implementation process. This section also discusses Partial (e.g.
night time only quiet zones) and Intermediate Quiet Zones. An
Intermediate Quiet Zone is one where horn restrictions were in
place after October 9, 1996, but as of December 18, 2003.
Section II of the Guide provides information on establishing New
Quiet Zones. A New Quiet Zone is one at which train horns are
currently being sounded at crossings. The Public Authority
Designation and Public Authority Application to FRA methods will be
discussed in depth.
Section III of the Guide provides information on establishing
Pre-Rule Quiet Zones. A Pre-Rule Quiet Zone is one where train
horns were not routinely sounded as of October 9, 1996 and December
18, 2003. The differences between New and Pre-Rule Quiet Zones will
be explained. Public Authority Designation and Public Authority
Application to FRA methods also apply to Pre-Rule Quiet Zones.
Section IV of the Guide deals with the required notifications
that must be provided by public authorities when establishing both
New and continuing Pre-Rule or Intermediate Quiet Zones.
Section V of the Guide provides examples of quiet zone
implementation.
Section I - Overview
In order for a quiet zone to be qualified under this rule, it
must be shown that the lack of the train horn does not present a
significant risk with respect to loss of life or serious personal
injury, or that the significant risk has been compensated for by
other means. The rule provides four basic ways in which a quiet
zone may be established. Creation of both New Quiet Zones and
Pre-Rule Quiet Zones are based on the same general guidelines;
however, there are a number of differences that will be noted in
the discussion on Pre-Rule Quiet Zones.
A. Qualifying Conditions
(1) One of the following four conditions or scenarios must be
met in order to show that the lack of the train horn does not
present a significant risk, or that the significant risk has been
compensated for by other means:
a. One or more SSMs as identified in appendix A are installed at
each public crossing in the quiet zone; or
b. The Quiet Zone Risk Index is equal to, or less than, the
Nationwide Significant Risk Threshold without implementation of
additional safety measures at any crossings in the quiet zone;
or
c. Additional safety measures are implemented at selected
crossings resulting in the Quiet Zone Risk Index being reduced to a
level equal to, or less than, the Nationwide Significant Risk
Threshold; or
d. Additional safety measures are taken at selected crossings
resulting in the Quiet Zone Risk Index being reduced to at least
the level of the Risk Index With Horns (that is, the risk that
would exist if train horns were sounded at every public crossing in
the quiet zone).
(2) It is important to consider the implications of each
approach before deciding which one to use. If a quiet zone is
qualified based on reference to the Nationwide Significant Risk
Threshold (i.e. the Quiet Zone Risk Index is equal to, or less
than, the Nationwide Significant Risk Threshold - see the second
and third scenarios above), then an annual review will be done by
FRA to determine if the Quiet Zone Risk Index remains equal to, or
less than, the Nationwide Significant Risk Threshold. Since the
Nationwide Significant Risk Threshold and the Quiet Zone Risk Index
may change from year to year, there is no guarantee that the quiet
zone will remain qualified. The circumstances that cause the
disqualification may not be subject to the control of the public
authority. For example, an overall national improvement in safety
at gated crossings may cause the Nationwide Significant Risk
Threshold to fall. This may cause the Quiet Zone Risk Index to
become greater than the Nationwide Significant Risk Threshold. If
the quiet zone is no longer qualified, then the public authority
will have to take additional measures, and may incur additional
costs that might not have been budgeted, to once again lower the
Quiet Zone Risk Index to at least the Nationwide Significant Risk
Threshold in order to retain the quiet zone. Therefore, while the
initial cost to implement a quiet zone under the second or third
scenario may be lower than the other options, these scenarios also
carry a degree of uncertainty about the quiet zone's continued
existence.
(3) The use of the first or fourth scenarios reduces the risk
level to at least the level that would exist if train horns were
sounding in the quiet zone. These methods may have higher initial
costs because more safety measures may be necessary in order to
achieve the needed risk reduction. Despite the possibility of
greater initial costs, there are several benefits to these methods.
The installation of SSMs at every crossing will provide the
greatest safety benefit of any of the methods that may be used to
initiate a quiet zone. With both of these methods (first and fourth
scenarios), the public authority will never need to be concerned
about the Nationwide Significant Risk Threshold, annual reviews of
the Quiet Zone Risk Index, or failing to be qualified because the
Quiet Zone Risk Index is higher than the Nationwide Significant
Risk Threshold. Public authorities are strongly encouraged to
carefully consider both the pros and cons of all of the methods and
to choose the method that will best meet the needs of its citizens
by providing a safer and quieter community.
(4) For the purposes of this Guide, the term “Risk Index with
Horns” is used to represent the level of risk that would exist if
train horns were sounded at every public crossing in the proposed
quiet zone. If a public authority decides that it would like to
fully compensate for the lack of a train horn and not install SSMs
at each public crossing in the quiet zone, it must reduce the Quiet
Zone Risk Index to a level that is equal to, or less than, the Risk
Index with Horns. The Risk Index with Horns is similar to the
Nationwide Significant Risk Threshold in that both are targets that
must be reached in order to establish a quiet zone under the rule.
Quiet zones that are established by reducing the Quiet Zone Risk
Index to at least the level of the Nationwide Significant Risk
Threshold will be reviewed annually by FRA to determine if they
still qualify under the rule to retain the quiet zone. Quiet zones
that are established by reducing the Quiet Zone Risk Index to at
least the level of the Risk Index with Horns will not be subject to
annual reviews.
(5) The use of FRA's web-based Quiet Zone Calculator is
recommended to aid in the decision making process
(http://www.fra.dot.gov/us/content/1337). The Quiet Zone
Calculator will allow the public authority to consider a variety of
options in determining which SSMs make the most sense. It will also
perform the necessary calculations used to determine the existing
risk level and whether enough risk has been mitigated in order to
create a quiet zone under this rule.
B. Risk Reduction Methods
FRA has established two general methods to reduce risk in order
to have a quiet zone qualify under this rule. The method chosen
impacts the manner in which the quiet zone is implemented.
1. Public Authority Designation (SSMs) - The Public
Authority Designation method (§ 222.39(a)) involves the use of SSMs
(see appendix A) at some or all crossings within the quiet zone.
The use of only SSMs to reduce risk will allow a public authority
to designate a quiet zone without approval from FRA. If the public
authority installs SSMs at every crossing within the quiet zone, it
need not demonstrate that they will reduce the risk sufficiently in
order to qualify under the rule since FRA has already assessed the
ability of the SSMs to reduce risk. In other words, the Quiet Zone
Calculator does not need to be used. However, if only SSMs are
installed within the quiet zone, but not at every crossing, the
public authority must calculate that sufficient risk reduction will
be accomplished by the SSMs. Once the improvements are made, the
public authority must make the required notifications (which
includes a copy of the report generated by the Quiet Zone
Calculator showing that the risk in the quiet zone has been
sufficiently reduced), and the quiet zone may be implemented. FRA
does not need to approve the plan as it has already assessed the
ability of the SSMs to reduce risk.
2. Public Authority Application to FRA (ASMs) - The
Public Authority Application to FRA method (§ 222.39(b)) involves
the use ASMs (see appendix B). ASMs include modified SSMs that do
not fully comply with the provisions found in appendix A (e.g.,
shorter than required traffic channelization devices),
non-engineering ASMs (e.g., programmed law enforcement), and
engineering ASMs (i.e., engineering improvements other than
modified SSMs). If the use of ASMs (or a combination of ASMs and
SSMs) is elected to reduce risk, then the public authority must
provide a Notice of Intent and then apply to FRA for approval of
the quiet zone. The application must contain sufficient data and
analysis to confirm that the proposed ASMs do indeed provide the
necessary risk reduction. FRA will review the application and will
issue a formal approval if it determines that risk is reduced to a
level that is necessary in order to comply with the rule. Once FRA
approval has been received and the safety measures fully
implemented, the public authority would then provide a Notice of
Quiet Zone Establishment and the quiet zone may be implemented. The
use of non-engineering ASMs will require continued monitoring and
analysis throughout the existence of the quiet zone to ensure that
risk continues to be reduced.
3. Calculating Risk Reduction - The following should be
noted when calculating risk reductions in association with the
establishment of a quiet zone. This information pertains to both
New Quiet Zones and Pre-Rule Quiet Zones and to the Public
Authority Designation and Public Authority Application to FRA
methods.
Crossing closures: If any public crossing within the
quiet zone is proposed to be closed, include that crossing when
calculating the Risk Index with Horns. The effectiveness of a
closure is 1.0. However, be sure to increase the traffic counts at
other crossings within the quiet zone and recalculate the risk
indices for those crossings that will handle the traffic diverted
from the closed crossing. It should be noted that crossing closures
that are already in existence are not considered in the risk
calculations.
Example:A proposed New Quiet Zone contains four crossings: A, B, C
and D streets. A, B and D streets are equipped with flashing lights
and gates. C Street is a passive crossbuck crossing with a traffic
count of 400 vehicles per day. It is decided that C Street will be
closed as part of the project. Compute the risk indices for all
four streets. The calculation for C Street will utilize flashing
lights and gates as the warning device. Calculate the Crossing
Corridor Risk Index by averaging the risk indices for all four of
the crossings. This value will also be the Risk Index with Horns
since train horns are currently being sounded. To calculate the
Quiet Zone Risk Index, first re-calculate the risk indices for B
and D streets by increasing the traffic count for each crossing by
200. (Assume for this example that the public authority decided
that the traffic from C Street would be equally divided between B
and D streets.) Increase the risk indices for A, B and D streets by
66.8% and divide the sum of the three remaining crossings by four.
This is the initial Quiet Zone Risk Index and accounts for the risk
reduction caused by closing C Street.
Grade Separation: Grade separated crossings that were in
existence before the creation of a quiet zone are not included in
any of the calculations. However, any public crossings within the
quiet zone that are proposed to be treated by grade separation
should be treated in the same manner as crossing closures. Highway
traffic that may be diverted from other crossings within the quiet
zone to the new grade separated crossing should be considered when
computing the Quiet Zone Risk Index.
Example:A proposed New Quiet Zone contains four crossings: A, B, C
and D streets. All streets are equipped with flashing lights and
gates. C Street is a busy crossing with a traffic count of 25,000
vehicles per day. It is decided that C Street will be grade
separated as part of the project and the existing at-grade crossing
closed. Compute the risk indices for all four streets. Calculate
the Crossing Corridor Risk Index, which will also be the Risk Index
with Horns, by averaging the risk indices for all four of the
crossings. To calculate the Quiet Zone Risk Index, first
re-calculate the risk indices for B and D streets by decreasing the
traffic count for each crossing by 1,200. (The public authority
decided that 2,400 motorists will decide to use the grade
separation at C Street in order to avoid possible delays caused by
passing trains.) Increase the risk indices for A, B and D streets
by 66.8% and divide the sum of the three remaining crossings by
four. This is the initial Quiet Zone Risk Index and accounts for
the risk reduction caused by the grade separation at C Street.
Pre-Existing SSMs: Risk reduction credit may be taken by
a public authority for a SSM that was previously implemented and is
currently in place in the quiet zone. If an existing improvement
meets the criteria for a SSM as provided in appendix A, the
improvement is deemed a Pre-Existing SSM. Risk reduction credit is
obtained by inflating the Risk Index With Horns to show what the
risk would have been at the crossing if the pre-existing SSM had
not been implemented. Crossing closures and grade separations that
occurred prior to the implementation of the quiet zone are not
Pre-Existing SSMs and do not receive any risk reduction credit.
Example 1.A proposed New Quiet Zone has one crossing that is
equipped with flashing lights and gates and has medians 100 feet in
length on both sides of the crossing. The medians conform to the
requirements in appendix A and qualify as a Pre-Existing SSM. The
risk index as calculated for the crossing is 10,000. To calculate
the Risk Index With Horns for this crossing, you divide the risk
index by difference between one and the effectiveness rate of the
pre-existing SSM (10,000 ÷ (1-0.75) = 40,000). This value (40,000)
would then be averaged in with the risk indices of the other
crossings to determine the proposed quiet zone's Risk Index With
Horns. To calculate the Quiet Zone Risk Index, the original risk
index is increased by 66.8% to account for the additional risk
attributed to the absence of the train horn (10,000 × 1.668 =
16,680). This value (16,680) is then averaged into the risk indices
of the other crossings that have also been increased by 66.8%. The
resulting average is the Quiet Zone Risk Index. Example 2.A
Pre-Rule Quiet Zone consisting of four crossings has one crossing
that is equipped with flashing lights and gates and has medians 100
feet in length on both sides of the crossing. The medians conform
to the requirements in appendix A and qualify as a Pre-Existing
SSM. The risk index as calculated for the crossing is 20,000. To
calculate the Risk Index With Horns for this crossing, first reduce
the risk index by 40 percent to reflect the risk reduction that
would be achieved if train horns were routinely sounded (20,000 ×
0.6 = 12,000). Next, divide the resulting risk index by difference
between one and the effectiveness rate of the pre-existing SSM
(12,000 ÷ (1 − 0.75) = 48,000). This value (48,000) would then be
averaged with the adjusted risk indices of the other crossings to
determine the pre-rule quiet zone's Risk Index With Horns. To
calculate the Quiet Zone Risk Index, the original risk index
(20,000) is then averaged into the risk original indices of the
other crossings. The resulting average is the Quiet Zone Risk
Index.
Pre-Existing Modified SSMs: Risk reduction credit may be
taken by a public authority for a modified SSM that was previously
implemented and is currently in place in the quiet zone. Modified
SSMs are Alternative Safety Measures which must be approved by FRA.
If an existing improvement is approved by FRA as a modified SSM as
provided in appendix B, the improvement is deemed a Pre-Existing
Modified SSM. Risk reduction credit is obtained by inflating the
Risk Index With Horns to show what the risk would have been at the
crossing if the pre-existing SSM had not been implemented. The
effectiveness rate of the modified SSM will be determined by FRA.
The public authority may provide information to FRA to be used in
determining the effectiveness rate of the modified SSM. Once an
effectiveness rate has been determined, follow the procedure
previously discussed for Pre-Existing SSMs to determine the risk
values that will be used in the quiet zone calculations.
Wayside Horns: Crossings with wayside horn installations
will be treated as a one for one substitute for the train horn and
are not to be included when calculating the Crossing Corridor Risk
Index, the Risk Index with Horns or the Quiet Zone Risk Index.
Example:A proposed New Quiet Zone contains four crossings: A, B, C
and D streets. All streets are equipped with flashing lights and
gates. It is decided that C Street will have a wayside horn
installed. Compute the risk indices for A, B and D streets. Since C
Street is being treated with a wayside horn, it is not included in
the calculation of risk. Calculate the Crossing Corridor Risk Index
by averaging the risk indices for A, B and D streets. This value is
also the Risk Index with Horns. Increase the risk indices for A, B
and D streets by 66.8% and average the results. This is the initial
Quiet Zone Risk Index for the proposed quiet zone. C. Partial Quiet
Zones
A Partial Quiet Zone is a quiet zone in which locomotive horns
are not routinely sounded at public crossings for a specified
period of time each day. For example, a quiet zone during only the
nighttime hours would be a partial quiet zone. Partial quiet zones
may be either New or Pre-Rule and follow the same rules as 24 hour
quiet zones. New Partial Quiet Zones must be in effect during the
hours of 10 p.m. to 7 a.m. All New Partial Quiet Zones must comply
with all of the requirements for New Quiet Zones. For example, all
public grade crossings that are open during the time that horns are
silenced must be equipped with flashing lights and gates that are
equipped with constant warning time (where practical) and power out
indicators. Risk is calculated in exactly the same manner as for
New Quiet Zones. The Quiet Zone Risk Index is calculated for the
entire 24-hour period, even though the train horn will only be
silenced during the hours of 10 p.m. to 7 a.m.
A Pre-Rule Partial Quiet Zone is a partial quiet zone at which
train horns were not sounding as of October 9, 1996 and on December
18, 2003. All of the regulations that pertain to Pre-Rule Quiet
Zones also pertain to Pre-Rule Partial Quiet Zones. The Quiet Zone
Risk Index is calculated for the entire 24-hour period for Pre-Rule
Partial Quiet Zones, even though train horns are only silenced
during the nighttime hours. Pre-Rule Partial Quiet Zones may
qualify for automatic approval in the same manner as Pre-Rule Quiet
Zones with one exception. If the Quiet Zone Risk Index is less than
twice the National Significant Risk Threshold, and there have been
no relevant collisions during the time period when train horns are
silenced, then the Pre-Rule Partial Quiet Zone is automatically
qualified. In other words, a relevant collision that occurred
during the period of time that train horns were sounded will not
disqualify a Pre-Rule Partial Quiet Zone that has a Quiet Zone Risk
Index that is less than twice the National Significant Risk Index.
Pre-Rule Partial Quiet Zones must provide the notification as
required in § 222.43 in order to keep train horns silenced. A
Pre-Rule Partial Quiet Zone may be converted to a 24 hour New Quiet
Zone by complying with all of the New Quiet Zone regulations.
D. Intermediate Quiet Zones
An Intermediate Quiet Zone is one where horn restrictions were
in place after October 9, 1996, but as of December 18, 2003 (the
publication date of the Interim Final Rule). Intermediate Quiet
Zones and Intermediate Partial Quiet Zones will be able to keep
train horns silenced until June 24, 2006, provided notification is
made per § 222.43. This will enable public authority to have
additional time to make the improvement necessary to come into
compliance with the rule. Intermediate Quiet Zones must conform to
all the requirements for New Quiet Zones by June 24, 2006. Other
than having the horn silenced for an additional year, Intermediate
Quiet Zones are treated exactly like New Quiet Zones.
Section II - New Quiet Zones
FRA has established several approaches that may be taken in
order to establish a New Quiet Zone under this rule. Please see the
preceding discussions on “Qualifying Conditions” and “Risk
Reduction Methods” to assist in the decision-making process on
which approach to take. This following discussion provides the
steps necessary to establish New Quiet Zones and includes both the
Public Authority Designation and Public Authority Application to
FRA methods. It must be remembered that in a New Quiet Zone all
public crossings must be equipped with flashing lights and gates.
The requirements are the same regardless of whether a 24-hour or
partial quiet zone is being created.
A. Requirements for Both Public Authority Designation and Public
Authority Application
The following steps are necessary when establishing a New Quiet
Zone. This information pertains to both the Public Authority
Designation and Public Authority Application to FRA methods.
1. The public authority must provide a written Notice of Intent
(§ 222.43(a)(1) and § 222.43(b)) to the railroads that operate over
the proposed quiet zone, the State agency responsible for highway
and road safety and the State agency responsible for grade crossing
safety. The purpose of this Notice of Intent is to provide an
opportunity for the railroads and the State agencies to provide
comments and recommendations to the public authority as it is
planning the quiet zone. They will have 60 days to provide these
comments to the public authority. The quiet zone cannot be created
unless the Notice of Intent has been provided. FRA encourages
public authorities to provide the required Notice of Intent early
in the quiet zone development process. The railroads and State
agencies can provide an expertise that very well may not be present
within the public authority. FRA believes that it will be very
useful to include these organizations in the planning process. For
example, including railroads and State agencies in the inspections
of the crossing will help ensure accurate Inventory information for
the crossings. The railroad can provide information on whether the
flashing lights and gates are equipped with constant warning time
and power out indicators. Pedestrian crossings and private
crossings with public access, industrial or commercial use that are
within the quiet zone must have a diagnostic team review and be
treated according to the team's recommendations. Railroads and the
State agency responsible for grade crossing safety must be invited
to the diagnostic team review. Note: Please see Section IV for
details on the requirements of a Notice of Intent.
2. Determine all public, private and pedestrian at-grade
crossings that will be included within the quiet zone. Also,
determine any existing grade-separated crossings that fall within
the quiet zone. Each crossing must be identified by the U.S. DOT
Crossing Inventory number and street or highway name. If a crossing
does not have a U.S. DOT Crossing Inventory number, then contact
FRA's Office of Safety (202-493-6299) for assistance.
3. Ensure that the quiet zone will be at least one-half mile in
length. (§ 222.35(a)(1)) If more than one New Quiet Zone or New
Partial Quiet Zone will be created within a single political
jurisdiction, ensure that each New Quiet Zone or New Partial Quiet
Zone will be separated by at least one public highway-rail grade
crossing. (§ 222.35(a)(1)(iii))
4. A complete and accurate Grade Crossing Inventory Form must be
on file with FRA for all crossings (public, private and pedestrian)
within the quiet zone. An inspection of each crossing in the
proposed quiet zone should be performed and the Grade Crossing
Inventory Forms updated, as necessary, to reflect the current
conditions at each crossing.
5. Every public crossing within the quiet zone must be equipped
with active warning devices comprising both flashing lights and
gates. The warning devices must be equipped with power out
indicators. Constant warning time circuitry is also required unless
existing conditions would prevent the proper operation of the
constant warning time circuitry. FRA recommends that these
automatic warning devices also be equipped with at least one bell
to provide an audible warning to pedestrians. If the warning
devices are already equipped with a bell (or bells), the bells may
not be removed or deactivated. The plans for the quiet zone may be
made assuming that flashing lights and gates are at all public
crossings; however the quiet zone may not be implemented until all
public crossings are actually equipped with the flashing lights and
gates. (§§ 222.35(b)(1) and 222.35(b)(2))
6. Private crossings must have cross-bucks and “STOP” signs on
both approaches to the crossing. Private crossings with public
access, industrial or commercial use must have a diagnostic team
review and be treated according to the team's recommendations. The
public authority must invite the State agency responsible for grade
crossing safety and all affected railroads to participate in the
diagnostic review. (§§ 222.25(b) and (c))
7. Each highway approach to every public and private crossing
must have an advance warning sign (in accordance with the MUTCD)
that advises motorists that train horns are not sounded at the
crossing, unless the public or private crossing is equipped with a
wayside horn. (§ 222.35(c))
8. Each pedestrian crossing must be reviewed by a diagnostic
team and equipped or treated in accordance with the recommendation
of the diagnostic team. The public authority must invite the State
agency responsible for grade crossing safety and all affected
railroads to participate in the diagnostic review. At a minimum,
each approach to every pedestrian crossing must be equipped with a
sign that conforms to the MUTCD and advises pedestrians that train
horns are not sounded at the crossing. (§ 222.27)
B. New Quiet Zones - Public Authority Designation
Once again it should be remembered that all public crossings
must be equipped with automatic warning devices consisting of
flashing lights and gates in accordance with § 222.35(b). In
addition, one of the following conditions must be met in order for
a public authority to designate a new quiet zone without FRA
approval:
a. One or more SSMs as identified in appendix A are installed at
each public crossing in the quiet zone (§ 222.39(a)(1));
or
b. The Quiet Zone Risk Index is equal to, or less than, the
Nationwide Significant Risk Threshold without SSMs installed at any
crossings in the quiet zone (§ 222.39(a)(2)(i)); or
c. SSMs are installed at selected crossings, resulting in the
Quiet Zone Risk Index being reduced to a level equal to, or less
than, the Nationwide Significant Risk Threshold (§
222.39(a)(2)(ii)); or
d. SSMs are installed at selected crossings, resulting in the
Quiet Zone Risk Index being reduced to a level of risk that would
exist if the horn were sounded at every crossing in the quiet zone
(i.e., the Risk Index with Horns) (§ 222.39(a)(3)).
Steps necessary to establish a New Quiet Zone using the Public
Authority Application to FRA method:
1. If one or more SSMs as identified in appendix A are installed
at each public crossing in the quiet zone, the requirements for a
public authority designation quiet zone will have been met. It is
not necessary for the same SSM to be used at each crossing.
However, before any improvements are implemented, the public
authority must provide a Notice of Intent, which will trigger a
60-day comment period. During the 60-day comment period, railroads
operating within the proposed quiet zone and State agencies
responsible for grade crossing, highway and road safety may submit
comments on the proposed quiet zone improvements to the public
authority. Once the necessary improvements have been installed,
Notice of Quiet Zone Establishment shall be provided and the quiet
zone implemented in accordance with the rule. If SSMs are not
installed at each public crossing, proceed on to Step 2 and use the
risk reduction method.
2. To begin, calculate the risk index for each public crossing
within the quiet zone (See appendix D. FRA's web-based Quiet Zone
Calculator may be used to do this calculation). If flashing lights
and gates have to be installed at any public crossings, calculate
the risk indices for such crossings as if lights and gates were
installed. (Note: Flashing lights and gates must be installed prior
to initiation of the quiet zone.) If the Inventory record does not
reflect the actual conditions at the crossing, be sure to use the
conditions that currently exist when calculating the risk index.
Note: Private crossings and pedestrian crossings are not included
when computing the risk for the proposed quiet zone.
3. The Crossing Corridor Risk Index is then calculated by
averaging the risk index for each public crossing within the
proposed quiet zone. Since train horns are routinely being sounded
for crossings in the proposed quiet zone, this value is also the
Risk Index with Horns.
4. In order to calculate the initial Quiet Zone Risk Index,
first adjust the risk index at each public crossing to account for
the increased risk due to the absence of the train horn. The
absence of the horn is reflected by an increased risk index of
66.8% at gated crossings. The initial Quiet Zone Risk Index is then
calculated by averaging the increased risk index for each public
crossing within the proposed quiet zone. At this point the Quiet
Zone Risk Index will equal the Risk Index with Horns multiplied by
1.668.
5. Compare the Quiet Zone Risk Index to the Nationwide
Significant Risk Threshold. If the Quiet Zone Risk Index is equal
to, or less than, the Nationwide Significant Risk Threshold, then
the public authority may decide to designate a quiet zone and
provide the Notice of Intent, followed by the Notice of Quiet Zone
Establishment. With this approach, FRA will annually recalculate
the Nationwide Significant Risk Threshold and the Quiet Zone Risk
Index. If the Quiet Zone Risk Index for the quiet zone rises above
the Nationwide Significant Risk Threshold, FRA will notify the
Public Authority so that appropriate measures can be taken. (See §
222.51(a)).
6. If the Quiet Zone Risk Index is greater than the Nationwide
Significant Risk Threshold, then select an appropriate SSM for a
crossing. Reduce the inflated risk index calculated in Step 4 for
that crossing by the effectiveness rate of the chosen SSM. (See
appendix A for the effectiveness rates for the various SSMs).
Recalculate the Quiet Zone Risk Index by averaging the revised
inflated risk index with the inflated risk indices for the other
public crossings. If this new Quiet Zone Risk Index is equal to, or
less than, the Nationwide Significant Risk Threshold, the quiet
zone would qualify for public authority designation. If the Quiet
Zone Risk Index is still higher than the Nationwide Significant
Risk Threshold, treat another public crossing with an appropriate
SSM and repeat the process until the Quiet Zone Risk Index is equal
to, or less than, the Nationwide Significant Risk Threshold. Once
this result is obtained, the quiet zone will qualify for
establishment by public authority designation. Early in the quiet
zone development process, a Notice of Intent should be provided by
the public authority, which will trigger a 60-day comment period.
During this 60-day comment period, railroads operating within the
proposed quiet zone and State agencies responsible for grade
crossing, highway and road safety may provide comments on the
proposed quiet zone improvements described in the Notice of Intent.
Once all the necessary safety improvements have been implemented,
Notice of Quiet Zone Establishment must be provided. With this
approach, FRA will annually recalculate the Nationwide Significant
Risk Threshold and the Quiet Zone Risk Index. If the Quiet Zone
Risk Index for the quiet zone rises above the Nationwide
Significant Risk Threshold, FRA will notify the public authority so
that appropriate measures can be taken. (See § 222.51(a)).
7. If the public authority wishes to reduce the risk of the
quiet zone to the level of risk that would exist if the horn were
sounded at every crossing within the quiet zone, the public
authority should calculate the initial Quiet Zone Risk Index as in
Step 4. The objective is to now reduce the Quiet Zone Risk Index to
the level of the Risk Index with Horns by adding SSMs at the
crossings. The difference between the Quiet Zone Risk Index and the
Risk Index with Horns is the amount of risk that will have to be
reduced in order to fully compensate for lack of the train horn.
The use of the Quiet Zone Calculator will aid in determining which
SSMs may be used to reduce the risk sufficiently. Follow the
procedure stated in Step 6, except that the Quiet Zone Risk Index
must be equal to, or less than, the Risk Index with Horns instead
of the Nationwide Significant Risk Threshold. Once this risk level
is attained, the quiet zone will qualify for establishment by
public authority designation. Early in the quiet zone development
process, a Notice of Intent should be provided by the public
authority, which will trigger a 60-day comment period. During this
60-day comment period, railroads operating within the proposed
quiet zone and State agencies responsible for grade crossing,
highway and road safety may provide comments on the proposed quiet
zone improvements described in the Notice of Intent. Once all the
necessary safety improvements have been implemented, Notice of
Quiet Zone Establishment must be provided. One important
distinction with this option is that the public authority will
never need to be concerned with the Nationwide Significant Risk
Threshold or the Quiet Zone Risk Index. The rule's intent is to
make the quiet zone as safe as if the train horns were sounding. If
this is accomplished, the public authority may designate the
crossings as a quiet zone and need not be concerned with possible
fluctuations in the Nationwide Significant Risk Threshold or annual
risk reviews.
C. New Quiet Zones - Public Authority Application to FRA
A public authority must apply to FRA for approval of a quiet
zone under three conditions. First, if any of the SSMs selected for
the quiet zone do not fully conform to the design standards set
forth in appendix A. These are referred to as modified SSMs in
appendix B. Second, when programmed law enforcement, public
education and awareness programs, or photo enforcement is used to
reduce risk in the quiet zone, these are referred to as
non-engineering ASMs in appendix B. It should be remembered that
non-engineering ASMs will require periodic monitoring as long as
the quiet zone is in existence. Third, when engineering ASMs are
used to reduce risk. Please see appendix B for detailed
explanations of ASMs and the periodic monitoring of non-engineering
ASMs.
The public authority is strongly encouraged to submit the
application to FRA for review and comment before the appendix B
treatments are initiated. This will enable FRA to provide comments
on the proposed ASMs to help guide the application process. If
non-engineering ASMs or engineering ASMs are proposed, the public
authority also may wish to confirm with FRA that the methodology it
plans to use to determine the effectiveness rates of the proposed
ASMs is appropriate. A quiet zone that utilizes a combination of
SSMs from appendix A and ASMs from appendix B must make a Public
Authority Application to FRA. A complete and thoroughly documented
application will help to expedite the approval process.
The following discussion is meant to provide guidance on the
steps necessary to establish a new quiet zone using the Public
Authority Application to FRA method. Once again it should be
remembered that all public crossings must be equipped with
automatic warning devices consisting of flashing lights and gates
in accordance with § 222.35(b).
1. Gather the information previously mentioned in the section on
“Requirements for both Public Authority Designation and Public
Authority Application.”
2. Calculate the risk index for each public crossing as directed
in Step 2 - Public Authority Designation.
3. Calculate the Crossing Corridor Risk Index, which is also the
Risk Index with Horns, as directed in Step 3 - Public Authority
Designation.
4. Calculate the initial Quiet Zone Risk Index as directed in
Step 4 - Public Authority Designation.
5. Begin to reduce the Quiet Zone Risk Index through the use of
ASMs and SSMs. Follow the procedure provided in Step 6 - Public
Authority Designation until the Quiet Zone Risk Index has been
reduced to equal to, or less than, either the Nationwide
Significant Risk Threshold or the Risk Index with Horns. (Remember
that the public authority may choose which level of risk reduction
is the most appropriate for its community.) Effectiveness rates for
ASMs should be provided as follows:
a. Modified SSMs - Estimates of effectiveness for modified SSMs
may be based upon adjustments from the effectiveness rates provided
in appendix A or from actual field data derived from the crossing
sites. The application must provide an estimated effectiveness rate
and the rationale for the estimate.
b. Non-engineering ASMs - Effectiveness rates are to be
calculated in accordance with the provisions of appendix B,
paragraph II B.
c. Engineering ASMs - Effectiveness rates are to be calculated
in accordance with the provisions of appendix B, paragraph III
B.
6. Once it has been determined through analysis that the Quiet
Zone Risk Index will be reduced to a level equal to, or less than,
either the Nationwide Significant Risk Threshold or the Risk Index
with Horns, the public authority must provide a Notice of Intent.
The mailing of the Notice of Intent will trigger a 60-day comment
period, during which railroads operating within the proposed quiet
zone and State agencies responsible for grade crossing, highway and
road safety may provide comments on the proposed quiet zone
improvements. After reviewing any comments received, the public
authority may make application to FRA for a quiet zone under §
222.39(b). FRA will review the application to determine the
appropriateness of the proposed effectiveness rates, and whether or
not the proposed application demonstrates that the quiet zone meets
the requirements of the rule. When submitting the application to
FRA for approval, the application must contain the following (§
222.39(b)(1)):
a. Sufficient detail concerning the present safety measures at
all crossings within the proposed quiet zone. This includes current
and accurate crossing inventory forms for each public, private, and
pedestrian grade crossing.
b. Detailed information on the safety improvements that are
proposed to be implemented at public, private and pedestrian grade
crossings within the proposed quiet zone.
c. Membership and recommendations of the diagnostic team (if
any) that reviewed the proposed quiet zone.
d. Statement of efforts taken to address comments submitted by
affected railroads, the State agency responsible for grade crossing
safety, and the State agency responsible for highway and road
safety, including a list of any objections raised by the railroads
or State agencies.
e. A commitment to implement the proposed safety measures.
f. Demonstrate through data and analysis that the proposed
measures will reduce the Quiet Zone Risk Index to a level equal to,
or less than, either the Nationwide Significant Risk Threshold or
the Risk Index with Horns.
g. A copy of the application must be provided to: All railroads
operating over the public highway-rail grade crossings within the
quiet zone; the highway or traffic control or law enforcement
authority having jurisdiction over vehicular traffic at grade
crossings within the quiet zone; the landowner having control over
any private crossings within the quiet zone; the State agency
responsible for highway and road safety; the State agency
responsible for grade crossing safety; and the Associate
Administrator. (§ 222.39(b)(3))
7. Upon receiving written approval from FRA of the quiet zone
application, the public authority may then provide the Notice of
Quiet Zone Establishment and implement the quiet zone. If the quiet
zone is qualified by reducing the Quiet Zone Risk Index to a level
at, or below, the Nationwide Significant Risk Threshold, FRA will
annually recalculate the Nationwide Significant Risk Threshold and
the Quiet Zone Risk Index. If the Quiet Zone Risk Index for the
quiet zone rises above the Nationwide Significant Risk Threshold,
FRA will notify the public authority so that appropriate measures
can be taken. (See § 222.51(a))
Note:
The provisions stated above for crossing closures, grade
separations, wayside horns, pre-existing SSMs and pre-existing
modified SSMs apply for Public Authority Application to FRA as
well.
Section III - Pre-Rule Quiet Zones
Pre-Rule Quiet Zones are treated slightly differently from New
Quiet Zones in the rule. This is a reflection of the statutory
requirement to “take into account the interest of communities that
have in effect restrictions on the sounding of a locomotive horn at
highway-rail grade crossings. * * *” (49 U.S.C. 20153(i)) It also
recognizes the historical experience of train horns not being
sounded at Pre-Rule Quiet Zones.
Overview
Pre-Rule Quiet Zones that are not established by automatic
approval (see discussion that follows) must meet the same
requirements as New Quiet Zones as provided in § 222.39. In other
words, risk must be reduced through the use of SSMs or ASMs so that
the Quiet Zone Risk Index for the quiet zone has been reduced to
either the risk level which would exist if locomotive horns sounded
at all crossings in the quiet zone (i.e. the Risk Index with
Horns) or to a risk level equal to, or less than, the Nationwide
Significant Risk Threshold. There are four differences in the
requirements between Pre-Rule Quiet Zones and New Quiet Zones that
must be noted.
(1) First, since train horns have not been routinely sounded in
the Pre-Rule Quiet Zone, it is not necessary to increase the risk
indices of the public crossings to reflect the additional risk
caused by the lack of a train horn. Since the train horn has
already been silenced, the added risk caused by the lack of a horn
is reflected in the actual collision history at the crossings.
Collision history is an important part in the calculation of the
severity risk indices. In other words, the Quiet Zone Risk Index is
calculated by averaging the existing risk index for each public
crossing without the need to increase the risk index by 66.8%. For
Pre-Rule Quiet Zones, the Crossing Corridor Risk Index and the
initial Quiet Zone Risk Index have the same value.
(2) Second, since train horns have been silenced at the
crossings, it will be necessary to mathematically determine what
the risk level would have been at the crossings if train horns had
been routinely sounded. These revised risk levels then will be used
to calculate the Risk Index with Horns. This calculation is
necessary to determine how much risk must be eliminated in order to
compensate for the lack of the train horn. This will allow the
public authority to have the choice to reduce the risk to at least
the level of the Nationwide Significant Risk Threshold or to fully
compensate for the lack of the train horn.
To calculate the Risk Index with Horns, the first step is to
divide the existing severity risk index for each crossing by the
appropriate value as shown in Table 1. This process eliminates the
risk that was caused by the absence of train horns. The table takes
into account that the train horn has been found to produce
different levels of effectiveness in preventing collisions
depending on the type of warning device at the crossing. (Note:
FRA's web-based Quiet Zone Calculator will perform this computation
automatically for Pre-Rule Quiet Zones.) The Risk Index with Horns
is the average of the revised risk indices. The difference between
the calculated Risk Index with Horns and the Quiet Zone Risk Index
is the amount of risk that would have to be reduced in order to
fully compensate for the lack of train horns.
Table 1 - Risk Index Divisor Values
Passive
Flashing lights
Lights
& gates
U.S
1.749
1.309
1.668
(3) The third difference is that credit is given for the risk
reduction that is brought about through the upgrading of the
warning devices at public crossings (§ 222.35(b)(3)). For New Quiet
Zones, all crossings must be equipped with automatic warning
devices consisting of flashing lights and gates. Crossings without
gates must have gates installed. The severity risk index for that
crossing is then calculated to establish the risk index that is
used in the Risk Index with Horns. The Risk Index with Horns is
then increased by 66.8% to adjust for the lack of the train horn.
The adjusted figure is the initial Quiet Zone Risk Index. There is
no credit received for the risk reduction that is attributable to
warning device upgrades in New Quiet Zones.
For Pre-Rule Quiet Zones, the Risk Index with Horns is
calculated from the initial risk indices which use the warning
devices that are currently installed. If a public authority elects
to upgrade an existing warning device as part of its quiet zone
plan, the accident prediction value for that crossing will be
re-calculated based on the upgraded warning device. (Once again,
FRA's web-based Quiet Zone Calculator can do the actual
computation.) The new accident prediction value is then used in the
severity risk index formula to determine the risk index for the
crossing. This adjusted risk index is then used to compute the new
Quiet Zone Risk Index. This computation allows the risk reduction
attributed to the warning device upgrades to be used in
establishing a quiet zone.
(4) The fourth difference is that Pre-Rule Quiet Zones have
different minimum requirements under § 222.35. A Pre-Rule Quiet
Zone may be less than one-half mile in length if that was its
length as of October 9, 1996 (§ 222.35(a)(2)). A Pre-Rule Quiet
Zone does not have to have automatic warning devices consisting of
flashing lights and gates at every public crossing (§
222.35(b)(3)). The existing crossing safety warning systems in
place as of December 18, 2003 may be retained but cannot be
downgraded. It also is not necessary for the automatic warning
devices to be equipped with constant warning time devices or power
out indicators; however, when the warning devices are upgraded,
constant warning time and power out indicators will be required if
reasonably practical (§ 222.35(b)(3)). Advance warning signs that
notify the motorist that train horns are not sounded do not have to
be installed on each approach to public, private, and pedestrian
grade crossings within the quiet zone until June 24, 2008. (§§
222.27(d) and 222.35(c)) Similarly, STOP signs and crossbucks do
not have to be installed on each approach to private crossings
within the quiet zone until June 24, 2008. (§ 222.25(c)).
A. Requirements for Both Public Authority Designation and Public
Authority Application - Pre-Rule Quiet Zones
The following is necessary when establishing a Pre-Rule Quiet
Zone. This information pertains to Automatic Approval, the Public
Authority Designation and Public Authority Application to FRA
methods.
1. Determine all public, private and pedestrian at-grade
crossings that will be included within the quiet zone. Also
determine any existing grade separated crossings that fall within
the quiet zone. Each crossing must be identified by the U.S. DOT
Crossing Inventory number and street name. If a crossing does not
have a U.S. DOT crossing number, then contact FRA for
assistance.
2. Document the length of the quiet zone. It is not necessary
that the quiet zone be at least one-half mile in length. Pre-Rule
Quiet Zones may be shorter than one-half mile. However, the
addition of a new crossing that is not a part of an existing
Pre-Rule Quiet Zone to a quiet zone nullifies its pre-rule status,
and the resulting New Quiet Zone must be at least one-half mile.
The deletion of a crossing from a Pre-Rule Quiet Zone (except
through closure or grade separation) must result in a quiet zone
that is at least one-half mile in length. It is the intent of the
rule to allow adjacent Pre-Rule Quiet Zones to be combined into one
large pre-rule quiet zone if the respective public authorities
desire to do so. (§ 222.35(a)(2))
3. A complete and accurate Grade Crossing Inventory Form must be
on file with FRA for all crossings (public, private and pedestrian)
within the quiet zone. An inspection of each crossing in the
proposed quiet zone should be performed and the Grade Crossing
Inventory Forms updated, as necessary, to reflect the current
conditions at each crossing.
4. Pre-Rule Quiet Zones must retain, and may upgrade, the
existing grade crossing safety warning systems. Unlike New Quiet
Zones, it is not necessary that every public crossing within a
Pre-Rule Quiet Zone be equipped with active warning devices
comprising both flashing lights and gates. Existing warning devices
need not be equipped with power out indicators and constant warning
time circuitry. If warning devices are upgraded to flashing lights,
or flashing lights and gates, the upgraded equipment must include,
as is required for New Quiet Zones, power out indicators and
constant warning time devices (if reasonably practical). (§
222.35(b)(3))
5. By June 24, 2008, private crossings must have cross-bucks and
“STOP” signs on both approaches to the crossing. (§ 222.25(c))
6. By June 24, 2008, each approach to a public, private, and
pedestrian crossing must be equipped with an advance warning sign
that conforms to the MUTCD and advises pedestrians and motorists
that train horns are not sounded at the crossing. (§§ 222.27(d),
222.35(c))
7. It will be necessary for the public authority to provide a
Notice of Quiet Zone Continuation in order to prevent the
resumption of locomotive horn sounding when the rule becomes
effective. A detailed discussion of the requirements of § 222.43(c)
is provided in Section IV of this appendix. The Notice of Quiet
Zone Continuation must be provided to the appropriate parties by
all Pre-Rule Quiet Zones that have not established quiet zones by
automatic approval. This should be done no later than June 3, 2005
to ensure that train horns will not start being sounded on June 24,
2005. A Pre-Rule Quiet Zone may provide a Notice of Quiet Zone
Continuation before it has determined whether or not it qualifies
for automatic approval. Once it has been determined that the
Pre-Rule Quiet Zone will be established by automatic approval, the
Public Authority must provide the Notice of Quiet Zone
Establishment. This must be accomplished no later than December 24,
2005. If the Pre-Rule Quiet Zone will not be established by
automatic approval, the Notice of Quiet Zone Continuation will
enable the train horns to be silenced until June 24, 2008. (Please
refer to § 222.41(c) for more information.)
B. Pre-Rule Quiet Zones - Automatic Approval
In order for a Pre-Rule Quiet Zone to be established under this
rule (§ 222.41(a)), one of the following conditions must be
met:
a. One or more SSMs as identified in appendix A are installed at
each public crossing in the quiet zone;
b. The Quiet Zone Risk Index is equal to, or less than, the
Nationwide Significant Risk Threshold;
c. The Quiet Zone Risk Index is above the Nationwide Significant
Risk Threshold but less than twice the Nationwide Significant Risk
Threshold and there have been no relevant collisions at any public
grade crossing within the quiet zone for the preceding five years;
or
d. The Quiet Zone Risk Index is equal to, or less than, the Risk
Index With Horns.
Additionally, the Pre-Rule Quiet Zone must be in compliance with
the minimum requirements for quiet zones (§ 222.35) and the
notification requirements in § 222.43.
The following discussion is meant to provide guidance on the
steps necessary to determine if a Pre-Rule Quiet Zone qualifies for
automatic approval.
1. All of the items listed in Requirements for Both Public
Authority Designation and Public Authority Application - Pre-Rule
Quiet Zones previously mentioned are to be accomplished.
Remember that a Pre-Rule Quiet Zone may be less than one-half mile
in length if that was its length as of October 9, 1996. Also, a
Pre-Rule Quiet Zone does not have to have automatic warning devices
consisting of flashing lights and gates at every public
crossing.
2. If one or more SSMs as identified in appendix A are installed
at each public crossing in the quiet zone, the quiet zone qualifies
and the public authority may provide the Notice of Quiet Zone
Establishment. If the Pre-Rule Quiet Zone does not qualify by this
step, proceed on to the next step.
3. Calculate the risk index for each public crossing within the
quiet zone (See appendix D.) Be sure that the risk index is
calculated using the formula appropriate for the type of warning
device that is actually installed at the crossing. Unlike New Quiet
Zones, it is not necessary to calculate the risk index using
flashing lights and gates as the warning device at every public
crossing. (FRA's web-based Quiet Zone Calculator may be used to
simplify the calculation process). If the Inventory record does not
reflect the actual conditions at the crossing, be sure to use the
conditions that currently exist when calculating the risk
index.
4. The Quiet Zone Risk Index is then calculated by averaging the
risk index for each public crossing within the proposed quiet zone.
(Note: The initial Quiet Zone Risk Index and the Crossing Corridor
Risk Index are the same for Pre-Rule Quiet Zones.)
5. Compare the Quiet Zone Risk Index to the Nationwide
Significant Risk Threshold. If the Quiet Zone Risk Index is equal
to, or less than, the Nationwide Significant Risk Threshold, then
the quiet zone qualifies, and the public authority may provide the
Notice of Quiet Zone Establishment. With this approach, FRA will
annually recalculate the Nationwide Significant Risk Threshold and
the Quiet Zone Risk. If the Quiet Zone Risk Index for the quiet
zone is found to be above the Nationwide Significant Risk
Threshold, FRA will notify the public authority so that appropriate
measures can be taken (See § 222.51(b)). If the Pre-Rule Quiet Zone
is not established by this step, proceed on to the next step.
6. If the Quiet Zone Risk Index is above the Nationwide
Significant Risk Threshold but less than twice the Nationwide
Significant Risk Threshold and there have been no relevant
collisions at any public grade crossing within the quiet zone for
the preceding five years, then the quiet zone qualifies for
automatic approval. However, in order to qualify on this basis, the
public authority must provide a Notice of Quiet Zone Establishment
by December 24, 2005. (Note: A relevant collision means a collision
at a highway-rail grade crossing between a train and a motor
vehicle, excluding the following: a collision resulting from an
activation failure of an active grade crossing warning system; a
collision in which there is no driver in the motor vehicle; or a
collision where the highway vehicle struck the side of the train
beyond the fourth locomotive unit or rail car.) With this approach,
FRA will annually recalculate the Nationwide Significant Risk
Threshold and the Quiet Zone Risk. If the Quiet Zone Risk Index for
the quiet zone is above two times the Nationwide Significant Risk
Threshold, or a relevant collision has occurred during the
preceding year, FRA will notify the public authority so that
appropriate measures can be taken (See § 222.51(b)).
If the Pre-Rule Quiet Zone is not established by automatic
approval, continuation of the quiet zone may require implementation
of SSMs or ASMs to reduce the Quiet Zone Risk Index for the quiet
zone to a risk level equal to, or below, either the risk level
which would exist if locomotive horns sounded at all crossings in
the quiet zone (i.e. the Risk Index with Horns) or the
Nationwide Significant Risk Threshold. This is the same methodology
used to create New Quiet Zones with the exception of the four
differences previously noted. A review of the previous discussion
on the two methods used to establish quiet zones may prove helpful
in determining which would be the most beneficial to use for a
particular Pre-Rule Quiet Zone.
C. Pre-Rule Quiet Zones - Public Authority Designation
The following discussion is meant to provide guidance on the
steps necessary to establish a Pre-Rule Quiet Zone using the Public
Authority Designation method.
1. The public authority must provide a Notice of Intent (§§
222.43(a)(1) and 222.43(b)) to the railroads that operate within
the proposed quiet zone, the State agency responsible for highway
and road safety and the State agency responsible for grade crossing
safety. This notice must be mailed by February 24, 2008, in order
to continue existing locomotive horn restrictions beyond June 24,
2008 without interruption. The purpose of this Notice of Intent is
to provide an opportunity for the railroads and the State agencies
to provide comments and recommendations to the public authority as
it is planning the quiet zone. They will have 60 days to provide
these comments to the public authority. The Notice of Intent must
be provided, if new SSMs or ASMs will be implemented within the
quiet zone. FRA encourages public authorities to provide the
required Notice of Intent early in the quiet zone development
process. The railroads and State agencies can provide an expertise
that very well may not be present within the public authority. FRA
believes that it will be very useful to include these organizations
in the planning process. For example, including them in the
inspections of the crossing will help ensure accurate Inventory
information for the crossings. Note: Please see Section IV for
details on the requirements of a Notice of Intent.
2. All of the items listed in “Requirements for Both Public
Authority Designation and Public Authority Application - Pre-Rule
Quiet Zones” previously mentioned are to be accomplished. Remember
that a Pre-Rule Quiet Zone may be less than one-half mile in length
if that was its length as of October 9, 1996. Also, a Pre-Rule
Quiet Zone does not have to have automatic warning devices
consisting of flashing lights and gates at every public
crossing.
3. Calculate the risk index for each public crossing within the
quiet zone as in Step 3 - Pre-Rule Quiet Zones - Automatic
Approval.
4. The Crossing Corridor Risk Index is then calculated by
averaging the risk index for each public crossing within the
proposed quiet zone. Since train horns are not being sounded for
crossings, this value is actually the initial Quiet Zone Risk
Index.
5. Calculate Risk Index with Horns by the following:
a. For each public crossing, divide the risk index that was
calculated in Step 2 by the appropriate value in Table 1. This
produces the risk index that would have existed had the train horn
been sounded.
b. Average these reduced risk indices together. The resulting
average is the Risk Index with Horns.
6. Begin to reduce the Quiet Zone Risk Index through the use of
SSMs or by upgrading existing warning devices. Follow the procedure
provided in Step 6 - Public Authority Designation until the Quiet
Zone Risk Index has been reduced to a level equal to, or less than,
either the Nationwide Significant Risk Threshold or the Risk Index
with Horns. A public authority may elect to upgrade an existing
warning device as part of its Pre-Rule Quiet Zone plan. When
upgrading a warning device, the accident prediction value for that
crossing must be re-calculated for the new warning device.
Determine the new risk index for the upgraded crossing by using the
new accident prediction value in the severity risk index formula.
This new risk index is then used to compute the new Quiet Zone Risk
Index. (Remember that FRA's web-based Quiet Zone Calculator will be
able to do the actual computations.) Once the Quiet Zone Risk Index
has been reduced to a level equal to, or less than, either the
Nationwide Significant Risk Threshold or the Risk Index with Horns,
the quiet zone may be established by the Public Authority
Designation method, and the public authority may provide the Notice
of Quiet Zone Establishment once all the necessary improvements
have been installed. If the quiet zone is established by reducing
the Quiet Zone Risk Index to a risk level equal to, or less than,
the Nationwide Significant Risk Threshold, FRA will annually
recalculate the Nationwide Significant Risk Threshold and the Quiet
Zone Risk Index. If the Quiet Zone Risk Index for the quiet zone
rises above the Nationwide Significant Risk Threshold, FRA will
notify the public authority so that appropriate measures can be
taken (See § 222.51(b)).
7. If the Pre-Rule Quiet Zone will not be established before
June 24, 2008, the public authority must file a detailed plan for
quiet zone improvements with the Associate Administrator by June
24, 2008. By providing a Notice of Intent (see Step 1 above) and a
detailed plan for quiet zone improvements, existing locomotive horn
restrictions may continue until June 24, 2010. (If a comprehensive
State-wide implementation plan and funding commitment are also
provided and safety improvements are initiated within at least one
Pre-Rule Quiet Zone or Pre-Rule Partial Quiet Zone, existing
locomotive horn restrictions may continue until June 24, 2013.)
(See § 222.41(c) for more information.)
Note:
The provisions stated above for crossing closures, grade
separations, wayside horns, pre-existing SSMs and pre-existing
modified SSMs apply for Public Authority Application to FRA as
well.
D. Pre-Rule Quiet Zones - Public Authority Application to FRA
The following discussion is meant to provide guidance on the
steps necessary to establish a Pre-Rule Quiet Zone using the Public
Authority Application to FRA method.
1. The public authority must provide a Notice of Intent (§§
222.43(a)(1) and 222.43(b)) to the railroads that operate within
the proposed quiet zone, the State agency responsible for highway
and road safety and the State agency responsible for grade crossing
safety. This notice must be mailed by February 24, 2008, in order
to continue existing locomotive horn restrictions beyond June 24,
2008 without interruption. The purpose of this Notice of Intent is
to provide an opportunity for the railroads and the State agencies
to provide comments and recommendations to the public authority as
it is planning the quiet zone. They will have 60 days to provide
these comments to the public authority. The Notice of Intent must
be provided, if new SSMs or ASMs will be implemented within the
quiet zone. FRA encourages public authorities to provide the
required Notice of Intent early in the quiet zone development
process. The railroads and State agencies can provide an expertise
that very well may not be present within the public authority. FRA
believes that it will be very useful to include these organizations
in the planning process. For example, including them in the
inspections of the crossing will help ensure accurate Inventory
information for the crossings. Note: Please see Section IV for
details on the requirements of a Notice of Detailed Plan.
2. All of the items listed in “Requirements for both Public
Authority Designation and Public Authority Application - Pre-Rule
Quiet Zones” previously mentioned are to be accomplished. Remember
that a Pre-Rule Quiet Zone may be less than one-half mile in length
if that was its length as of October 9, 1996. Also, a Pre-Rule
Quiet Zone does not have to have automatic warning devices
consisting of flashing lights and gates at every public
crossing.
3. Calculate the risk index for each public crossing within the
quiet zone (See appendix D. FRA's web-based Quiet Zone Calculator
may be used to simplify the calculation process). If the Inventory
record does not reflect the actual conditions at the crossing, be
sure to use the conditions that currently exist when calculating
the risk index.
4. The Crossing Corridor Risk Index is then calculated by
averaging the risk index for each public crossing within the
proposed quiet zone. Since train horns are not being sounded for
crossings, this value is actually the initial Quiet Zone Risk
Index.
5. Calculate Risk Index with Horns by the following:
a. For each public crossing, divide its risk index that was
calculated in Step 2 by the appropriate value in Table 1. This
produces the risk index that would have existed had the train horn
been sounded.
b. Average these reduced risk indices together. The resulting
average is the Risk Index with Horns.
6. Begin to reduce the Quiet Zone Risk Index through the use of
ASMs and/or SSMs. Follow the procedure provided in Step 6 - New
Quiet Zones Public Authority Designation - until the Quiet Zone
Risk Index has been reduced to a level equal to, or less than,
either the Nationwide Significant Risk Threshold or the Risk Index
with Horns. A public authority may elect to upgrade an existing
warning device as part of its Pre-Rule Quiet Zone plan. When
upgrading a warning device, the accident prediction value for that
crossing must be re-calculated for the new warning device.
Determine the new risk index for the upgraded crossing by using the
new accident prediction value in the severity risk index formula.
(Remember that FRA's web-based quiet zone risk calculator will be
able to do the actual computations.) This new risk index is then
used to compute the new Quiet Zone Risk Index. Effectiveness rates
for ASMs should be provided as follows:
a. Modified SSMs - Estimates of effectiveness for modified SSMs
may be based upon adjustments from the benchmark levels provided in
appendix A or from actual field data derived from the crossing
sites. The application must provide an estimated effectiveness rate
and the rationale for the estimate.
b. Non-engineering ASMs - Effectiveness rates are to be
calculated in accordance with the provisions of appendix B, section
II B.
c. Engineering ASMs - Effectiveness rates are to be calculated
in accordance with the provisions of appendix B, section III B.
7. Once it has been determined through analysis that the Quiet
Zone Risk Index will be reduced to a level equal to, or less than,
either the Nationwide Significant Risk Threshold or the Risk Index
with Horns, the public authority may make application to FRA for a
quiet zone under § 222.39(b). FRA will review the application to
determine the appropriateness of the proposed effectiveness rates,
and whether or not the proposed application demonstrates that the
quiet zone meets the requirements of the rule. When submitting the
application to FRA for approval, it should be remembered that the
application must contain the following (§ 222.39(b)(1)):
a. Sufficient detail concerning the present safety measures at
all crossings within the proposed quiet zone to enable the
Associate Administrator to evaluate their effectiveness. This
includes current and accurate crossing Inventory forms for each
public, private and pedestrian grade crossing.
b. Detailed information on the safety improvements, including
upgraded warning devices that are proposed to be implemented at
public, private, and pedestrian grade crossings within the proposed
quiet zone.
c. Membership and recommendations of the diagnostic team (if
any) that reviewed the proposed quiet zone.
d. Statement of efforts taken to address comments submitted by
affected railroads, the State agency responsible for grade crossing
safety, and the State agency responsible for highway and road
safety, including a list of any objections raised by the railroads
or State agencies.
e. A commitment to implement the proposed safety measures.
f. Demonstrate through data and analysis that the proposed
measures will reduce the Quiet Zone Risk Index to a level at, or
below, either the Nationwide Significant Risk Threshold or the Risk
Index with Horns.
g. A copy of the application must be provided to all railroads
operating over the public highway-rail grade crossings within the
quiet zone; the highway or traffic control or law enforcement
authority having jurisdiction over vehicular traffic at grade
crossings within the quiet zone; the landowner having control over
any private crossings within the quiet zone; the State agency
responsible for highway and road safety; the State agency
responsible for grade crossing safety; and the Associate
Administrator. (§ 222.39(b)(3))
8. Upon receiving written approval from FRA of the quiet zone
application, the public authority may then provide the Notice of
Quiet Zone Establishment and implement the quiet zone. If the quiet
zone is established by reducing the Quiet Zone Risk Index to a
level equal to, or less than, the Nationwide Significant Risk
Threshold, FRA will annually recalculate the Nationwide Significant
Risk Threshold and the Quiet Zone Risk. If the Quiet Zone Risk
Index for the quiet zone is above the Nationwide Significant Risk
Threshold, FRA will notify the public authority so that appropriate
measures can be taken (See § 222.51(b)).
Note:
The provisions stated above for crossing closures, grade
separations, wayside horns, pre-existing SSMs and pre-existing
modified SSMs apply for Public Authority Application to FRA as
well.
Section IV - Required Notifications A. Introduction
The public authority is responsible for providing notification
to parties that will be affected by the quiet zone. There are
several different types of notifications and a public authority may
have to make more than one notification during the entire process
of complying with the regulation. The notification process is to
ensure that interested parties are made aware in a timely manner of
the establishment or continuation of quiet zones. It will also
provide an opportunity for State agencies and affected railroads to
provide input to the public authority during the development of
quiet zones. Specific information is to be provided so that the
crossings in the quiet zone can be identified. Providing the
appropriate notification is important because once the rule becomes
effective, railroads will be obligated to sound train horns when
approaching all public crossings unless notified in accordance with
the rule that a New Quiet Zone has been established or that a
Pre-Rule or Intermediate Quiet Zone is being continued.
B. Notice of Intent - § 222.43(b)
The purpose of the Notice of Intent is to provide notice to the
railroads and State agencies that the public authority is planning
on creating a New Quiet Zone or implementing new SSMs or ASMs
within a Pre-Rule Quiet Zone. The Notice of Intent provides an
opportunity for the railroad and the State agencies to give input
to the public authority during the quiet zone development process.
The State agencies and railroads will be given sixty days to
provide information and comments to the public agency.
The Notice of Intent must be provided under the following
circumstances:
1. A New Quiet Zone or New Partial Quiet Zone is under
consideration.
2. An Intermediate Quiet Zone or Intermediate Partial Quiet Zone
that will be converted into a New Quiet Zone or New Partial Quiet
Zone. Please note that Notice of Intent must be mailed by April 3,
2006, in order prevent the resumption of locomotive horn sounding
on June 24, 2006.
3. The implementation of SSMs or ASMs within a Pre-Rule Quiet
Zone or Pre-Rule Partial Quiet Zone is under consideration. Please
note that Notice of Intent must be mailed by February 24, 2008, in
order to continue existing restrictions on locomotive horn sounding
beyond June 24, 2008 without interruption. Each public authority
that is creating a New Quiet Zone must provide written notice, by
certified mail, return receipt requested, to the following:
1. All railroads operating within the proposed quiet zone
2. State agency responsible for highway and road safety
3. State agency responsible for grade crossing safety
The Notice of Intent must contain the following information:
1. A list of each public highway-rail grade crossing, private
highway-rail grade crossing, and pedestrian crossings within the
proposed quiet zone. The crossings are to be identified by both the
U.S. DOT Crossing Inventory Number and the street or highway
name.
2. A statement of the time period within which the restrictions
would be in effect on the routine sounding of train horns
(i.e., 24 hours or from 10 p.m. to 7 a.m.).
3. A brief explanation of the public authority's tentative plans
for implementing improvements within the proposed quiet zone.
4. The name and title of the person who will act as the point of
contact during the quiet zone development process and how that
person can be contacted.
5. A list of the names and addresses of each party that will
receive a copy of the Notice of Intent.
The parties that receive the Notice of Intent will be able to
submit information or comments to the public authority for 60 days.
The public authority will not be able to establish the quiet zone
during the 60 day comment period unless each railroad and State
agency that receives the Notice of Intent provides either written
comments to the public authority or a written statement waiving its
right to provide comments on the Notice of Intent. The public
authority must provide an affirmation in the Notice of Quiet Zone
Establishment that each of the required parties was provided the
Notice of Intent and the date it was mailed. If the quiet zone is
being established within 60 days of the mailing of the Notice of
Intent, the public authority also must affirm each of the parties
have provided written comments or waived its right to provide
comments on the Notice of Intent.
C. Notice of Quiet Zone Continuation - § 222.43(c)
The purpose of the Notice of Quiet Zone Continuation is to
provide a means for the public authority to formally advise
affected parties that an existing quiet zone is being continued
after the effective date of the rule. All Pre-Rule, Pre-Rule
Partial, Intermediate and Intermediate Partial Quiet Zones must
provide this Notice of Quiet Zone Continuation no later than June
3, 2005 to ensure that train horns are not sounded at public
crossings when the rule becomes effective on June 24, 2005. This
will enable railroads to properly comply with the requirements of
the Final Rule.
Each public authority that is continuing an existing Pre-Rule,
Pre-Rule Partial, Intermediate and Intermediate Partial Quiet Zone
must provide written notice, by certified mail, return receipt
requested, to the following:
1. All railroads operating over the public highway-rail grade
crossings within the quiet zone;
2. The highway or traffic control or law enforcement authority
having jurisdiction over vehicular traffic at grade crossings
within the quiet zone;
3. The landowner having control over any private crossings
within the quiet zone;
4. The State agency responsible for highway and road safety;
5. The State agency responsible for grade crossing safety;
and
6. The Associate Administrator.
The Notice of Quiet Zone Continuation must contain the following
information:
1. A list of each public highway-rail grade crossing, private
highway-rail grade crossing, and pedestrian crossing within the
quiet zone, identified by both U.S. DOT National Highway-Rail Grade
Crossing Inventory Number and street or highway name.
2. A specific reference to the regulatory provision that
provides the basis for quiet zone continuation, citing as
appropriate, § 222.41 or 222.42.
3. A statement of the time period within which restrictions on
the routine sounding of the locomotive horn will be imposed (i.e.,
24 hours or nighttime hours only.)
4. An accurate and complete Grade Crossing Inventory Form for
each public highway-rail grade crossing, private highway-rail grade
crossing, and pedestrian crossing within the quiet zone that
reflects conditions currently existing at the crossing.
5. The name and title of the person responsible for monitoring
compliance with the requirements of this part and the manner in
which that person can be contacted.
6. A list of the names and addresses of each party that will
receive the Notice of Quiet Zone Continuation.
7. A statement signed by the chief executive officer of each
public authority participating in the continuation of the quiet
zone, in which the chief executive officer certifies that the
information submitted by the public authority is accurate and
complete to the best of his/her knowledge and belief.
Public authorities should remember that this notice is required
to ensure that train horns will remain silent. Even if a public
authority has not been able to determine whether its Pre-Rule or
Pre-Rule Partial Quiet Zone qualifies for automatic approval under
the rule, it should issue a Notice of Quiet Zone Continuation to
keep the train horns silent after the effective date of the
rule.
E. Notice of Quiet Zone Establishment - § 222.43(d)
The purpose of the Notice of Quiet Zone Establishment is to
provide a means for the public authority to formally advise
affected parties that a quiet zone is being established. Notice of
Quiet Zone Establishment must be provided under the following
circumstances:
1. A New Quiet Zone or New Partial Quiet Zone is being
created.
2. A Pre-Rule Quiet Zone or a Pre-Rule Partial Quiet Zone that
qualifies for automatic approval under the rule is being
established.
3. An Intermediate Quiet Zone or Intermediate Partial Quiet Zone
that is creating a New Quiet Zone under the rule. Please note that
Notice of Quiet Zone Establishment must be provided by June 3,
2006, in order to prevent the resumption of locomotive horn
sounding on June 24, 2006.
4. A Pre-Rule Quiet Zone or a Pre-Rule Partial Quiet Zone that
was not established by automatic approval and has since implemented
improvements to establish a quiet zone in accordance to the
rule.
Each public authority that is establishing a quiet zone under
the above circumstances must provide written notice, by certified
mail, return receipt requested, to the following:
1. All railroads operating over the public highway-rail grade
crossings within the quiet zone;
2. The highway or traffic control or law enforcement authority
having jurisdiction over vehicular traffic at grade crossings
within the quiet zone;
3. The landowner having control over any private crossings
within the quiet zone;
4. The State agency responsible for highway and road safety;
5. The State agency responsible for grade crossing safety;
and
6. The Associate Administrator.
The Notice of Quiet Establishment must contain the following
information:
1. A list of each public highway-rail grade crossing, private
highway-rail grade crossing, and pedestrian crossing within the
quiet zone, identified by both U.S. DOT National Highway-Rail Grade
Crossing Inventory Number and street or highway name.
2. A specific reference to the regulatory provision that
provides the basis for quiet zone establishment, citing as
appropriate, § 222.39(a)(1), 222.39(a)(2)(i), 222.39(a)(2)(ii),
222.39(a)(3), 222.39(b), 222.41(a)(1)(i), 222.41(a)(1)(ii),
222.41(a)(1)(iii), 222.41(a)(1)(iv), 222.41(b)(1)(i),
222.41(b)(1)(ii), 222.41(b)(1)(iii), or 222.41(b)(1)(iv).
(a) If the Notice of Quiet Establishment contains a specific
reference to § 222.39(a)(2)(i), 222.39(a)(2)(ii), 222.39(a)(3),
222.41(a)(1)(ii), 222.41(a)(1)(iii), 222.41(a)(1)(iv),
222.41(b)(1)(ii), 222.41(b)(1)(iii), or 222.41(b)(1)(iv), it shall
include a copy of the FRA web page that contains the quiet zone
data upon which the public authority is relying.
(b) If the Notice of Quiet Establishment contains a specific
reference to § 222.39(b), it shall include a copy of FRA's
notification of approval.
3. If a diagnostic team review was required under § 222.25
(private crossings) or § 222.27 (pedestrian crossings), the Notice
of Quiet Establishment shall include a statement affirming that the
State agency responsible for grade crossing safety and all affected
railroads were provided an opportunity to participate in the
diagnostic team review. The Notice of Quiet Establishment shall
also include a list of recommendations made by the diagnostic
team.
4. A statement of the time period within which restrictions on
the routine sounding of the locomotive horn will be imposed (i.e.,
24 hours or from 10 p.m. until 7 a.m.)
5. An accurate and complete Grade Crossing Inventory Form for
each public highway-rail grade crossing, private highway-rail grade
crossing, and pedestrian crossing within the quiet zone that
reflects the conditions existing at the crossing before any new
SSMs or ASMs were implemented.
6. An accurate, complete and current Grade Crossing Inventory
Form for each public highway-rail grade crossing, private
highway-rail grade crossing, and pedestrian crossing within the
quiet zone that reflects SSMs and ASMs in place upon establishment
of the quiet zone. SSMs and ASMs that cannot be fully described on
the Inventory Form shall be separately described.
7. If the public authority was required to provide a Notice of
Intent:
(a) The Notice of Quiet Zone Establishment shall contain a
statement affirming that the Notice of Intent was provided in
accordance with the rule. This statement shall also state the date
on which the Notice of Intent was mailed.
(b) If the Notice of Quiet Zone Establishment will be mailed
less than 60 days after the date on which the Notice of Intent was
mailed, the Notice of Quiet Zone Establishment shall also contain a
written statement affirming that comments and/or written waiver
statements have been received from each railroad operating over
public grade crossings within the proposed quiet zone, the State
agency responsible for grade crossing safety, and the State agency
responsible for highway and road safety.
8. The name and title of the person responsible for monitoring
compliance with the requirements of this part and the manner in
which that person can be contacted.
9. A list of the names and addresses of each party that is
receiving a copy of the Notice of Quiet Establishment.
10. A statement signed by the chief executive officer of each
public authority participating in the establishment of the quiet
zone, in which the chief executive officer shall certify that the
information submitted by the public authority is accurate and
complete to the best of his/her knowledge and belief.
Section V - Examples of Quiet Zone Implementations Example 1 - New
Quiet Zone
(a) A public authority wishes to create a New Quiet Zone over
four public crossings. All of the crossings are equipped with
flashing lights and gates, and the length of the quiet zone is 0.75
mile. There are no private crossings within the proposed zone.
(b) The tables that follow show the street name in the first
column, and the existing risk index for each crossing with the horn
sounding (“Crossing Risk Index w/ Horns”) in the second. The third
column, “Crossing Risk Index w/o Horns”, is the risk index for each
crossing after it has been inflated by 66.8% to account for the
lack of train horns. The fourth column, “SSM Eff”, is the
effectiveness of the SSM at the crossing. A zero indicates that no
SSM has been applied. The last column, “Crossing Risk Index w/o
Horns Plus SSM”, is the inflated risk index for the crossing after
being reduced by the implementation of the SSM. At the bottom of
the table are two values. The first is the Risk Index with Horns
(“RIWH”) which represents the average initial amount of risk in the
proposed quiet zone with the train horn sounding. The second is the
Quiet Zone Risk Index (“QZRI”), which is the average risk in the
proposed quiet zone taking into consideration the increased risk
caused by the lack of train horns and the reductions in risk
attributable to the installation of SSMs. For this example it is
assumed that the Nationwide Significant Risk Threshold is 17,030.
In order for the proposed quiet zone to qualify under the rule, the
Quiet Zone Risk Index must be reduced to a level at, or below, the
Nationwide Significant Risk Threshold (17,030) or the Risk Index
with Horns.
(c) Table 2 shows the existing conditions in the proposed quiet
zone. SSMs have not yet been installed. The Risk Index with Horns
for the proposed quiet zone is 11,250. The Quiet Zone Risk Index
without any SSMs is 18,765.
Table 2
Street
Crossing
risk index
w/horns
Crossing
risk index
w/o horns
SSM EFF
Crossing
risk index
w/o horns
plus SSM
A
12000
20016
0
20016
B
10000
16680
0
16680
C
8000
13344
0
13344
D
15000
25020
0
25020
RIWH
QZRI
11250
18765
(d) The public authority decides to install traffic
channelization devices at D Street. Reducing the risk at the
crossing that has the highest severity risk index will provide the
greatest reduction in risk. The effectiveness of traffic
channelization devices is 0.75. Table 3 shows the changes in the
proposed quiet zone corridor that would occur when traffic
channelization devices are installed at D Street. The Quiet Zone
Risk Index has been reduced to 14,073.75. This reduction in risk
would qualify the quiet zone as the risk has been reduced lower
than the Nationwide Significant Risk Threshold which is 17,030.
Table 3
Street
Crossing
risk index
w/horns
Crossing
risk index
w/o horns
SSM EFF
Crossing
risk index
w/o horns
plus SSM
A
12000
20016
0
20016
B
10000
16680
0
16680
C
8000
13344
0
13344
D
15000
25020
0.75
6255
RIWH
QZRI
11250
14073.75
(e) The public authority realizes that reducing the Quiet Zone
Risk Index to a level below the Nationwide Significant Risk
Threshold will result in an annual re-calculation of the Quiet Zone
Risk Index and comparison to the Nationwide Significant Risk
Threshold. As the Quiet Zone Risk Index is close to the Nationwide
Significant Risk Threshold (14,074 to 17,030), there is a
reasonable chance that the Quiet Zone Risk Index may some day
exceed the Nationwide Significant Risk Threshold. This would result
in the quiet zone no longer being qualified and additional steps
would have to be taken to keep the quiet zone. Therefore, the
public authority decides to reduce the risk further by the use of
traffic channelization devices at A Street. Table 4 shows the
results of this change. The Quiet Zone Risk Index is now 10,320.75
which is less than the Risk Index with Horns of 11,250. The quiet
zone now qualifies by fully compensating for the loss of train
horns and will not have to undergo annual reviews of the Quiet Zone
Risk Index.
Table 4
Street
Crossing
risk index
w/horns
Crossing
risk index
w/o horns
SSM EFF
Crossing
risk index
w/o horns
plus SSM
A
12000
20016
0.75
5004
B
10000
16680
0
16680
C
8000
13344
0
13344
D
15000
25020
0.75
6255
RIWH
QZRI
11250
10320.75
Example 2 - Pre-Rule Quiet Zone
(a) A public authority wishes to qualify a Pre-Rule Quiet Zone
which did not meet the requirements for Automatic Approval because
the Quiet Zone Risk Index is greater than twice the Nationwide
Significant Risk Threshold. There are four public crossings in the
Pre-Rule Quiet Zone. Three of the crossings are equipped with
flashing lights and gates, and the fourth (Z Street) is passively
signed with a STOP sign. The length of the quiet zone is 0.6 mile,
and there are no private crossings within the proposed zone.
(b) The tables that follow are very similar to the tables in
Example 1. The street name is shown in the first column, and the
existing risk index for each crossing (“Crossing Risk Index w/o
Horns”) in the second. This is a change from the first example
because the risk is calculated without train horns sounding because
of the existing ban on whistles. The third column, “Crossing Risk
Index w/ Horns”, is the risk index for each crossing after it has
been adjusted to reflect what the risk would have been had train
horns been sounding. This is mathematically done by dividing the
existing risk index for the three gated crossing by 1.668. The risk
at the passive crossing at Z Street is divided by 1.749. (See the
above discussion in “Pre-Rule Quiet Zones - Establishment Overview”
for more information.) The fourth column, “SSM Eff”, is the
effectiveness of the SSM at the crossing. A zero indicates that no
SSM has been applied. The last column, “Crossing Risk Index w/o
Horns Plus SSM”, is the risk index without horns for the crossing
after being reduced for the implementation of the SSM. At the
bottom of the table are two values. The first is the Risk Index
with Horns (RIWH), which represents the average initial amount of
risk in the proposed quiet zone with the train horn sounding. The
second is the Quiet Zone Risk Index (“QZRI”), which is the average
risk in the proposed quiet zone taking into consideration the
increased risk caused by the lack of train horns and reductions in
risk attributable to the installation of SSMs. Once again it is
assumed that the Nationwide Significant Risk Threshold is 17,030.
The Quiet Zone Risk Index must be reduced to either the Nationwide
Significant Risk Threshold (17,030) or to the Risk Index with Horns
in order to qualify under the rule.
(c) Table 5 shows the existing conditions in the proposed quiet
zone. SSMs have not yet been installed. The Risk Index with Horns
for the proposed quiet zone is 18,705.83. The Quiet Zone Risk Index
without any SSMs is 31,375. Since the Nationwide Significant Risk
Threshold is less than the calculated Risk Index with Horns, the
public authority's goal will be to reduce the risk to at least
value of the Risk Index with Horns. This will qualify the Pre-Rule
Quiet Zone under the rule.
Table 5
Street
Crossing
risk index
w/o horns
Crossing
risk index
w/ horns
SSM EFF
Crossing
risk index
w/o horns
plus SSM
W
35,000
20,983.21
0
35,000
X
42,000
25,179.86
0
42,000
Y
33,500
20,083.93
0
33,500
Z
15,000
8,576.33
0
15,000
RIWH
QZRI
18,705.83
31,375
(d) The Z Street crossing is scheduled to have flashing lights
and gates installed as part of the state's highway-rail grade
crossing safety improvement plan (Section 130). While this upgrade
is not directly a part of the plan to authorize a quiet zone, the
public authority may take credit for the risk reduction achieved by
the improvement from a passive STOP sign crossing to a crossing
equipped with flashing lights and gates. Unlike New Quiet Zones,
upgrades to warning devices in Pre-Rule Quiet Zones do contribute
to the risk reduction necessary to qualify under the rule. Table 6
shows the quiet zone corridor after including the warning device
upgrade at Z Street. The Quiet Zone Risk Index has been reduced to
29,500.
Table 6
Street
Crossing
risk index
w/o horns
Crossing
risk index
w/ horns
SSM EFF
Crossing
risk index
w/o horns
plus SSM
W
35,000
20,983.21
0
35,000
X
42,000
25,179.86
0
42,000
Y
33,500
20,083.93
0
33,500
Z
7,500
8,576.33
0
7,500
RIWH
QZRI
18,705.83
29,500
(e) The public authority elects to install four-quadrant gates
without vehicle presence detection at X Street. As shown in Table
7, this reduces the Quiet Zone Risk Index to 20,890. This risk
reduction is not sufficient to quality as quiet zone under the
rule.
Table 7
Street
Crossing
risk index
w/o horns
Crossing
risk index
w/ horns
SSM EFF
Crossing
risk index
w/o horns
plus SSM
W
35,000
20,983.21
0
35,000
X
42,000
25,179.86
0.82
7,560
Y
33,500
20,083.93
0
33,500
Z
7,500
8,576.33
0
7,500
RIWH
QZRI
18,705.83
20,890
(f) The public authority next decides to use traffic
channelization devices at W Street. Table 8 shows that the Quiet
Zone Risk Index is now reduced to 14,327.5. This risk reduction
fully compensates for the loss of the train horn as it is less than
the Risk Index with Horns. The quiet zone is qualified under the
rule.