Table 1 to Subpart MMMM of Part 60—Model Rule—Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units
Comply with these increments of progress
By these dates a
Increment 1—Submit final control plan
(Dates to be specified in state plan)
Increment 2—Final compliance
(Dates to be specified in state plan) b
a Site-specific schedules can be used at the discretion of the state.
b The date can be no later than 3 years after the effective date of state plan approval or March 21, 2016 for SSI units that commenced construction on or before October 14, 2010.