40:8.0.1.1.1.39.298 | SUBJGRP 298
| Introduction | |
40:8.0.1.1.1.39.298.1 | SECTION 60.5000
| 60.5000 What is the purpose of this subpart | |
40:8.0.1.1.1.39.298.2 | SECTION 60.5005
| 60.5005 Am I affected by this subpart | |
40:8.0.1.1.1.39.298.3 | SECTION 60.5010
| 60.5010 Is a state plan required for all states | |
40:8.0.1.1.1.39.298.4 | SECTION 60.5015
| 60.5015 What must I include in my state plan | |
40:8.0.1.1.1.39.298.5 | SECTION 60.5020
| 60.5020 Is there an approval process for my state plan | |
40:8.0.1.1.1.39.298.6 | SECTION 60.5025
| 60.5025 What if my state plan is not approvable | |
40:8.0.1.1.1.39.298.7 | SECTION 60.5030
| 60.5030 Is there an approval process for a negative declaration letter | |
40:8.0.1.1.1.39.298.8 | SECTION 60.5035
| 60.5035 What compliance schedule must I include in my state plan | |
40:8.0.1.1.1.39.298.9 | SECTION 60.5040
| 60.5040 Are there any state plan requirements for this subpart that apply instead of the requirements specified in subpart B | |
40:8.0.1.1.1.39.298.10 | SECTION 60.5045
| 60.5045 In lieu of a state plan submittal, are there other acceptable option(s) for a state to meet its section 111(d)/129 (b)(2) obligations | |
40:8.0.1.1.1.39.298.11 | SECTION 60.5050
| 60.5050 What authorities will not be delegated to state, local, or tribal agencies | |
40:8.0.1.1.1.39.298.12 | SECTION 60.5055
| 60.5055 Does this subpart directly affect SSI unit owners and operators in my state | |
40:8.0.1.1.1.39.299 | SUBJGRP 299
| Applicability of State Plans | |
40:8.0.1.1.1.39.299.13 | SECTION 60.5060
| 60.5060 What SSI units must I address in my state plan | |
40:8.0.1.1.1.39.299.14 | SECTION 60.5065
| 60.5065 What SSI units are exempt from my state plan | |
40:8.0.1.1.1.39.300 | SUBJGRP 300
| Use of Model Rule | |
40:8.0.1.1.1.39.300.15 | SECTION 60.5070
| 60.5070 What is the “model rule” in this subpart | |
40:8.0.1.1.1.39.300.16 | SECTION 60.5075
| 60.5075 How does the model rule relate to the required elements of my state plan | |
40:8.0.1.1.1.39.300.17 | SECTION 60.5080
| 60.5080 What are the principal components of the model rule | |
40:8.0.1.1.1.39.301 | SUBJGRP 301
| Model Rule - Increments of Progress | |
40:8.0.1.1.1.39.301.18 | SECTION 60.5085
| 60.5085 What are my requirements for meeting increments of progress and achieving final compliance | |
40:8.0.1.1.1.39.301.19 | SECTION 60.5090
| 60.5090 When must I complete each increment of progress | |
40:8.0.1.1.1.39.301.20 | SECTION 60.5095
| 60.5095 What must I include in the notifications of achievement of increments of progress | |
40:8.0.1.1.1.39.301.21 | SECTION 60.5100
| 60.5100 When must I submit the notifications of achievement of increments of progress | |
40:8.0.1.1.1.39.301.22 | SECTION 60.5105
| 60.5105 What if I do not meet an increment of progress | |
40:8.0.1.1.1.39.301.23 | SECTION 60.5110
| 60.5110 How do I comply with the increment of progress for submittal of a control plan | |
40:8.0.1.1.1.39.301.24 | SECTION 60.5115
| 60.5115 How do I comply with the increment of progress for achieving final compliance | |
40:8.0.1.1.1.39.301.25 | SECTION 60.5120
| 60.5120 What must I do if I close my SSI unit and then restart it | |
40:8.0.1.1.1.39.301.26 | SECTION 60.5125
| 60.5125 What must I do if I plan to permanently close my SSI unit and not restart it | |
40:8.0.1.1.1.39.302 | SUBJGRP 302
| Model Rule - Operator Training and Qualification | |
40:8.0.1.1.1.39.302.27 | SECTION 60.5130
| 60.5130 What are the operator training and qualification requirements | |
40:8.0.1.1.1.39.302.28 | SECTION 60.5135
| 60.5135 When must the operator training course be completed | |
40:8.0.1.1.1.39.302.29 | SECTION 60.5140
| 60.5140 How do I obtain my operator qualification | |
40:8.0.1.1.1.39.302.30 | SECTION 60.5145
| 60.5145 How do I maintain my operator qualification | |
40:8.0.1.1.1.39.302.31 | SECTION 60.5150
| 60.5150 How do I renew my lapsed operator qualification | |
40:8.0.1.1.1.39.302.32 | SECTION 60.5155
| 60.5155 What if all the qualified operators are temporarily not accessible | |
40:8.0.1.1.1.39.302.33 | SECTION 60.5160
| 60.5160 What site-specific documentation is required and how often must it be reviewed by qualified operators and plant personnel | |
40:8.0.1.1.1.39.303 | SUBJGRP 303
| Model Rule - Emission Limits, Emission Standards, and Operating Limits and Requirements | |
40:8.0.1.1.1.39.303.34 | SECTION 60.5165
| 60.5165 What emission limits and standards must I meet and by when | |
40:8.0.1.1.1.39.303.35 | SECTION 60.5170
| 60.5170 What operating limits and requirements must I meet and by when | |
40:8.0.1.1.1.39.303.36 | SECTION 60.5175
| 60.5175 How do I establish operating limits if I do not use a wet scrubber, fabric filter, electrostatic precipitator, activated carbon injection, or afterburner, or if I limit emissions in some other manner, to comply with the emission limits | |
40:8.0.1.1.1.39.303.37 | SECTION 60.5180
| 60.5180 Do the emission limits, emission standards, and operating limits apply during periods of startup, shutdown, and malfunction | |
40:8.0.1.1.1.39.303.38 | SECTION 60.5181
| 60.5181 How do I establish an affirmative defense for exceedance of an emission limit or standard during malfunction | |
40:8.0.1.1.1.39.304 | SUBJGRP 304
| Model Rule - Initial Compliance Requirements | |
40:8.0.1.1.1.39.304.39 | SECTION 60.5185
| 60.5185 How and when do I demonstrate initial compliance with the emission limits and standards | |
40:8.0.1.1.1.39.304.40 | SECTION 60.5190
| 60.5190 How do I establish my operating limits | |
40:8.0.1.1.1.39.304.41 | SECTION 60.5195
| 60.5195 By what date must I conduct the initial air pollution control device inspection and make any necessary repairs | |
40:8.0.1.1.1.39.304.42 | SECTION 60.5200
| 60.5200 How do I develop a site-specific monitoring plan for my continuous monitoring, bag leak detection, and ash handling systems, and by what date must I conduct an initial performance evaluation | |
40:8.0.1.1.1.39.305 | SUBJGRP 305
| Model Rule - Continuous Compliance Requirements | |
40:8.0.1.1.1.39.305.43 | SECTION 60.5205
| 60.5205 How and when do I demonstrate continuous compliance with the emission limits and standards | |
40:8.0.1.1.1.39.305.44 | SECTION 60.5210
| 60.5210 How do I demonstrate continuous compliance with my operating limits | |
40:8.0.1.1.1.39.305.45 | SECTION 60.5215
| 60.5215 By what date must I conduct annual air pollution control device inspections and make any necessary repairs | |
40:8.0.1.1.1.39.306 | SUBJGRP 306
| Model Rule - Performance Testing, Monitoring, and Calibration Requirements | |
40:8.0.1.1.1.39.306.46 | SECTION 60.5220
| 60.5220 What are the performance testing, monitoring, and calibration requirements for compliance with the emission limits and standards | |
40:8.0.1.1.1.39.306.47 | SECTION 60.5225
| 60.5225 What are the monitoring and calibration requirements for compliance with my operating limits | |
40:8.0.1.1.1.39.307 | SUBJGRP 307
| Model Rule - Recordkeeping and Reporting | |
40:8.0.1.1.1.39.307.48 | SECTION 60.5230
| 60.5230 What records must I keep | |
40:8.0.1.1.1.39.307.49 | SECTION 60.5235
| 60.5235 What reports must I submit | |
40:8.0.1.1.1.39.308 | SUBJGRP 308
| Model Rule - Title V Operating Permits | |
40:8.0.1.1.1.39.308.50 | SECTION 60.5240
| 60.5240 Am I required to apply for and obtain a Title V operating permit for my existing SSI unit | |
40:8.0.1.1.1.39.308.51 | SECTION 60.5245
| 60.5245 When must I submit a title V permit application for my existing SSI unit | |
40:8.0.1.1.1.39.309 | SUBJGRP 309
| Model Rule-Definitions | |
40:8.0.1.1.1.39.309.52 | SECTION 60.5250
| 60.5250 What definitions must I know | |
40:8.0.1.1.1.39.310.53.61 | APPENDIX
| Table 1 to Subpart MMMM of Part 60 - Model Rule - Increments of Progress and Compliance Schedules for Existing Sewage Sludge Incineration Units | |
40:8.0.1.1.1.39.310.53.62 | APPENDIX
| Table 2 to Subpart MMMM of Part 60 - Model Rule - Emission Limits and Standards for Existing Fluidized Bed Sewage Sludge Incineration Units | |
40:8.0.1.1.1.39.310.53.63 | APPENDIX
| Table 3 to Subpart MMMM of Part 60 - Model Rule - Emission Limits and Standards for Existing Multiple Hearth Sewage Sludge Incineration Units | |
40:8.0.1.1.1.39.310.53.64 | APPENDIX
| Table 4 to Subpart MMMM of Part 60 - Model Rule - Operating Parameters for Existing Sewage Sludge Incineration Units a | |
40:8.0.1.1.1.39.310.53.65 | APPENDIX
| Table 5 to Subpart MMMM of Part 60 - Model Rule - Toxic Equivalency Factors | |
40:8.0.1.1.1.39.310.53.66 | APPENDIX
| Table 6 to Subpart MMMM of Part 60 - Model Rule - Summary of Reporting Requirements for Existing Sewage Sludge Incineration Units a | |