148.325 How soon after deepwater port decommissioning must the licensee initiate removal
§ 148.325 How soon after deepwater port decommissioning must the licensee initiate removal?Within 2 years of deepwater port decommissioning, the licensee must initiate removal procedures. The Commandant (CG-5P) will advise and coordinate with appropriate Federal agencies and the States concerning activities covered by this section.
[USCG-2013-0397, 78 FR 39177, July 1, 2013]