§ 750.307 FHWA project approval.

23 CFR 750.307

Citation23 CFR 750.307
CorpusDaily eCFR
Displayed edition2026-09-11
Last updated2026-09-11

§ 750.307 FHWA project approval.

Authorization to proceed with acquisitions on a sign removal project shall not be issued until such time as the State has submitted to FHWA the following:

(a) A general description of the project.

(b) The total number of signs to be acquired.

(c) The total estimated cost of the sign removal project, including a breakdown of incidental, acquisition and removal costs.