Title 7

SECTION 799.51

799.51 When an EIS is required.

§ 799.51 When an EIS is required.

(a) The following FSA proposed actions normally require preparation of an EIS:

(1) Legislative proposals, not including appropriations requests, with the potential for significant environmental impact that are drafted and submitted to Congress by FSA;

(2) Broad Federal assistance programs administered by FSA, involving significant financial assistance or payments to program participants, that may have significant cumulative impacts on the human environment; and

(3) Ongoing programs that have been found through previous environmental analyses to have major environmental concerns.

(b) [Reserved]