§ 217.524 Mitigation requirements.

(a) When conducting the specified activities identified in § 217.520(b), the mitigation measures contained in this section and any LOA issued under this subpart must be implemented.

(1) A copy of any issued LOA must be in the possession of State Parks, its designees, and work crew personnel operating under the authority of this LOA.

(2) State Parks must ensure that construction supervisors and crews, the monitoring team, and relevant State Parks staff are trained prior to the start of activities subject to the LOA, so that responsibilities, communication procedures, monitoring protocols, and operational procedures are clearly understood. New personnel joining during the project must be trained prior to commencing work.

(3) State Parks must employ Protected Species Observers (PSOs) and establish monitoring locations as described in any issued LOA and the relevant Marine Mammal Monitoring Plan (Monitoring Plan). State Parks must monitor the project area to the maximum extent possible based on the required number of PSOs, the required monitoring locations, and environmental conditions.

(4) Monitoring must take place from 30 minutes prior to initiation of pile driving activity (i.e., pre-start clearance monitoring) through 30 minutes post-completion of pile-driving activity.

(5) Pre-start clearance monitoring must be conducted during periods of visibility sufficient for the lead PSO to determine that the shutdown zones indicated in the LOA are clear of marine mammals. Pile driving may commence following 30 minutes of observation when the determination is made that the shutdown zones are clear of marine mammals.

(6) If a marine mammal is observed entering or within the shutdown zones indicated in the LOA, pile driving activity must be delayed or halted. Pile driving must be commenced or resumed as described in any issued LOA.

(7) If pile driving is delayed or halted due to the presence of a marine mammal, the activity may not commence or resume until either the animal has voluntarily exited and been visually confirmed beyond the shutdown zone indicated in the LOA or 15 minutes have passed without re-detection of the animal.

(8) State Parks must use soft start techniques when impact pile driving. Soft start requires contractors to provide an initial set of three strikes at reduced energy, followed by a 30-second waiting period, then two subsequent sets of reduced energy strikes. A soft start must be implemented at the start of each day's impact pile driving and at any time following cessation of impact pile driving for a period of 30 minutes or longer.

(9) State Parks must use a bubble curtain during impact pile driving. The bubble curtain must be operated as necessary to achieve optimal performance. At a minimum, State Parks must adhere to the following performance standards:

(i) The bubble curtain must distribute air bubbles around 100 percent of the piling circumference for the full depth of the water column.

(ii) The lowest bubble ring must be in contact with the substrate for the full circumference of the ring, and the weights attached to the bottom ring shall ensure 100 percent substrate contact. No parts of the ring or other objects shall prevent full substrate contact.

(iii) Air flow to the bubblers must be balanced around the circumference of the pile.

(10) Pile driving activity must be halted (as described in any issued LOA) upon observation of either a species for which incidental take is not authorized or a species for which incidental take has been authorized, but the authorized number of takes has been met, entering or within the harassment zone (as shown in the LOA).

(11) State Parks, construction supervisors and crews, PSOs, and relevant State Parks staff must avoid direct physical interaction with marine mammals during construction activity. If a marine mammal comes within 10 meters of such activity, operations must cease, and vessels must reduce speed to the minimum level required to maintain steerage and safe working conditions, as necessary to avoid direct physical interaction.

(b) [Reserved]