Title 48
SECTION 9.406-3
9.406-3 Procedures.
9.406-3 Procedures.(a) Investigation and referral. Agencies shall establish procedures for the prompt reporting, investigation, and referral to the debarring official of matters appropriate for that official's consideration.
(b) Decisionmaking process. (1) Agencies shall establish procedures governing the debarment decisionmaking process that are as informal as is practicable, consistent with principles of fundamental fairness. These procedures shall afford the contractor (and any specifically named affiliates) an opportunity to submit, in person, in writing, or through a representative, information and argument in opposition to the proposed debarment.
(2) In actions not based upon a conviction or civil judgment, if it is found that the contractor's submission in opposition raises a genuine dispute over facts material to the proposed debarment, agencies shall also -
(i) Afford the contractor an opportunity to appear with counsel, submit documentary evidence, present witnesses, and confront any person the agency presents; and
(ii) Make a transcribed record of the proceedings and make it available at cost to the contractor upon request, unless the contractor and the agency, by mutual agreement, waive the requirement for a transcript.
(c) Notice of proposal to debar. A notice of proposed debarment shall be issued by the debarring official advising the contractor and any specifically named affiliates, by certified mail, return receipt requested -
(1) That debarment is being considered;
(2) Of the reasons for the proposed debarment in terms sufficient to put the contractor on notice of the conduct or transaction(s) upon which it is based;
(3) Of the cause(s) relied upon under 9.406-2 for proposing debarment;
(4) That, within 30 days after receipt of the notice, the contractor may submit, in person, in writing, or through a representative, information and argument in opposition to the proposed debarment, including any additional specific information that raises a genuine dispute over the material facts;
(5) Of the agency's procedures governing debarment decisionmaking;
(6) Of the effect of the issuance of the notice of proposed debarment; and
(7) Of the potential effect of an actual debarment.
(d) Debarring official's decision. (1) In actions based upon a conviction or civil judgment, or in which there is no genuine dispute over material facts, the debarring official shall make a decision on the basis of all the information in the administrative record, including any submission made by the contractor. If no suspension is in effect, the decision shall be made within 30 working days after receipt of any information and argument submitted by the contractor, unless the debarring official extends this period for good cause.
(2)(i) In actions in which additional proceedings are necessary as to disputed material facts, written findings of fact shall be prepared. The debarring official shall base the decision on the facts as found, together with any information and argument submitted by the contractor and any other information in the administrative record.
(ii) The debarring official may refer matters involving disputed material facts to another official for findings of fact. The debarring official may reject any such findings, in whole or in part, only after specifically determining them to be arbitrary and capricious or clearly erroneous.
(iii) The debarring official's decision shall be made after the conclusion of the proceedings with respect to disputed facts.
(3) In any action in which the proposed debarment is not based upon a conviction or civil judgment, the cause for debarment must be established by a preponderance of the evidence.
(e) Notice of debarring official's decision. (1) If the debarring official decides to impose debarment, the contractor and any affiliates involved shall be given prompt notice by certified mail, return receipt requested -
(i) Referring to the notice of proposed debarment;
(ii) Specifying the reasons for debarment;
(iii) Stating the period of debarment, including effective dates; and
(iv) Advising that the debarment is effective throughout the executive branch of the Government unless the head of an agency or a designee makes the statement called for by 9.406-1(c).
(2) If debarment is not imposed, the debarring official shall promptly notify the contractor and any affiliates involved, by certified mail, return receipt requested.
(f)(1) If the contractor enters into an administrative agreement with the Government in order to resolve a debarment proceeding, the debarring official shall access the website (available at https://www.cpars.gov, then select FAPIIS) and enter the requested information.
(2) The debarring official is responsible for the timely submission, within 3 working days, and accuracy of the documentation regarding the administrative agreement.
(3) With regard to information that may be covered by a disclosure exemption under the Freedom of Information Act, the debarring official shall follow the procedures at 9.105-2(b)(2)(iv).
[48 FR 42142, Sept. 19, 1983, as amended at 54 FR 19815, May 8, 1989; 59 FR 67033, Dec. 28, 1994; 75 FR 14066, Mar. 23, 2010; 77 FR 201, Jan. 3, 2012; 83 FR 42572, Aug. 22, 2018; 84 FR 19845, May 6, 2019]