Title 48
SECTION 52.222-5
52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work.
52.222-5 Construction Wage Rate Requirements - Secondary Site of the Work.As prescribed in 22.407(h), insert the following provision:
Construction Wage Rate Requirements - Secondary Site of the Work (MAY 2014)(a)(1) The offeror shall notify the Government if the offeror intends to perform work at any secondary site of the work, as defined in paragraph (a)(1)(ii) of the FAR clause at 52.222-6, Construction Wage Rate Requirements, of this solicitation.
(2) If the offeror is unsure if a planned work site satisfies the criteria for a secondary site of the work, the offeror shall request a determination from the Contracting Officer.
(b)(1) If the wage determination provided by the Government for work at the primary site of the work is not applicable to the secondary site of the work, the offeror shall request a wage determination from the Contracting Officer.
(2) The due date for receipt of offers will not be extended as a result of an offeror's request for a wage determination for a secondary site of the work.
(End of provision) [70 FR 33667, June 8, 2005, as amended at 79 FR 24217, Apr. 29, 2014]