Title 47
SECTION 1.1412
1.1412 Contractors for survey and make-ready.
§ 1.1412 Contractors for survey and make-ready.(a) Contractors for self-help complex and above the communications space make-ready. A utility shall make available and keep up-to-date a reasonably sufficient list of contractors it authorizes to perform self-help surveys and make-ready that is complex and self-help surveys and make-ready that is above the communications space on its poles. The new attacher must use a contractor from this list to perform self-help work that is complex or above the communications space. New and existing attachers may request the addition to the list of any contractor that meets the minimum qualifications in paragraphs (c)(1) through (5) of this section and the utility may not unreasonably withhold its consent.
(b) Contractors for simple work. A utility may, but is not required to, keep up-to-date a reasonably sufficient list of contractors it authorizes to perform surveys and simple make-ready. If a utility provides such a list, then the new attacher must choose a contractor from the list to perform the work. New and existing attachers may request the addition to the list of any contractor that meets the minimum qualifications in paragraphs (c)(1) through (5) of this section and the utility may not unreasonably withhold its consent.
(1) If the utility does not provide a list of approved contractors for surveys or simple make-ready or no utility-approved contractor is available within a reasonable time period, then the new attacher may choose its own qualified contractor that meets the requirements in paragraph (c) of this section. When choosing a contractor that is not on a utility-provided list, the new attacher must certify to the utility that its contractor meets the minimum qualifications described in paragraph (c) of this section when providing notices required by § 1.1411(i)(1)(ii), (i)(2)(i), (j)(3)(i), and (j)(4).
(2) The utility may disqualify any contractor chosen by the new attacher that is not on a utility-provided list, but such disqualification must be based on reasonable safety or reliability concerns related to the contractor's failure to meet any of the minimum qualifications described in paragraph (c) of this section or to meet the utility's publicly available and commercially reasonable safety or reliability standards. The utility must provide notice of its contractor objection within the notice periods provided by the new attacher in § 1.1411(i)(1)(ii), (i)(2)(i), (j)(3)(i), and (j)(4) and in its objection must identify at least one available qualified contractor.
(c) Contractor minimum qualification requirements. Utilities must ensure that contractors on a utility-provided list, and new attachers must ensure that contractors they select pursuant to paragraph (b)(1) of this section, meet the following minimum requirements:
(1) The contractor has agreed to follow published safety and operational guidelines of the utility, if available, but if unavailable, the contractor shall agree to follow National Electrical Safety Code (NESC) guidelines;
(2) The contractor has acknowledged that it knows how to read and follow licensed-engineered pole designs for make-ready, if required by the utility;
(3) The contractor has agreed to follow all local, state, and federal laws and regulations including, but not limited to, the rules regarding Qualified and Competent Persons under the requirements of the Occupational and Safety Health Administration (OSHA) rules;
(4) The contractor has agreed to meet or exceed any uniformly applied and reasonable safety and reliability thresholds set by the utility, if made available; and
(5) The contractor is adequately insured or will establish an adequate performance bond for the make-ready it will perform, including work it will perform on facilities owned by existing attachers.
(d) The consulting representative of an electric utility may make final determinations, on a nondiscriminatory basis, where there is insufficient capacity and for reasons of safety, reliability, and generally applicable engineering purposes.
[76 FR 26640, May 9, 2011. Redesignated and amended at 83 FR 44842, Sept. 4, 2018; 83 FR 46839, Sept. 14, 2018]