eCFR.io
Daily eCFR

§ 3715.3-1 At what point may I begin occupancy?

43 CFR 3715.3-1

Citation43 CFR 3715.3-1
CorpusDaily eCFR
Displayed edition2026-08-12
Last updated2026-08-12

§ 3715.3-1 At what point may I begin occupancy?

You must not begin occupancy until—

(a) You have complied with either 43 CFR part 3800, subpart 3802 or 3809 and this subpart, and BLM has completed its review and made the required determinations under the applicable subparts, and

(b) You have obtained all federal, state and local mining, reclamation, and waste disposal permits, approvals, or other authorizations for the particular use or occupancy as required under this subpart.