§ 3264.12 What must I submit to BLM after I abandon a well?

43 CFR 3264.12

Citation43 CFR 3264.12
CorpusDaily eCFR
Displayed edition2026-08-12
Last updated2026-08-12

§ 3264.12 What must I submit to BLM after I abandon a well?

Send us a well abandonment report within 30 days after you abandon a well. If you plan to restore the site at a later date, you may submit a separate report within 30 days after completing site restoration. The well abandonment report must contain:

(a) A complete chronology of all work done;

(b) A description of each plug, including:

(1) Type and amount of cement used;

(2) Depth that the drill pipe or tubing was run to set the plug;

(3) Depth to top of plug; and

(4) If the plug was verified, whether it was done by tagging or pressure testing; and

(c) A description of surface restoration procedures.