Subpart 3271—Utilization Operations: Getting a Permit
Sections
-
3271.10
§ 3271.10 What do I need to start preparing a site and building and testing a utilization facility on Federal land leased for geothermal resources? -
3271.11
§ 3271.11 Who may apply for a permit to build a utilization facility? -
3271.12
§ 3271.12 What do I need to start preliminary site investigations that may disturb the surface? -
3271.13
§ 3271.13 How do I obtain approval to build pipelines and facilities connecting the well field to utilization facilities not located on Federal lands leased for geothermal resources? -
3271.14
§ 3271.14 What do I need to do to start building and testing a utilization facility if it is not located on Federal lands leased for geothermal resources? -
3271.15
§ 3271.15 How do I get a permit to begin commercial operations?