35.10045 Threshold criteria.

§ 35.10045 Threshold criteria.

(a) To be eligible to receive Federal credit assistance under this part, a project shall meet the following six threshold criteria:

(1) The project and obligor shall be creditworthy;

(2) The project sponsor shall submit a project application to the Administrator;

(3) A project shall have eligible project costs that are reasonably anticipated to equal or exceed $20 million, or for a project eligible under paragraphs (2) or (3) of 33 U.S.C. 3905 serving a community of not more than 25,000 individuals, project costs that are reasonably anticipated to equal or exceed $5 million;

(4) Project financing shall be repayable, in whole or in part, from State or local taxes, user fees, or other dedicated revenue sources that also secure the senior project obligations of the project; shall include a rate covenant, coverage requirement, or similar security feature supporting the project obligations; and may have a lien on revenues subject to any lien securing project obligations;

(5) In the case of a project that is undertaken by an entity that is not a State or local government or an agency or instrumentality of a State or local government, or a tribal government or consortium of tribal governments, the project that the entity is undertaking shall be publicly sponsored.

(6) The applicant shall have developed an operations and maintenance plan that identifies adequate revenues to operate, maintain, and repair the project during its useful life.

(b) With respect to paragraph (a)(4) of this section, the Administrator may accept general obligation pledges or general corporate promissory pledges and will determine the acceptability of other pledges and forms of collateral as dedicated revenue sources on a case-by-case basis. The Administrator shall not accept a pledge of Federal funds, regardless of source, as security for the WIFIA credit instrument.