Title 40

PART 62 SUBPART LLL

Subpart LLL - Federal Plan Requirements for Sewage Sludge Incineration Units Constructed on or Before October 14, 2010 Source:81 FR 26063, Apr. 29, 2016, unless otherwise noted.

40:10.0.1.1.2.64.1014SUBJGRP 1014
Applicability
40:10.0.1.1.2.64.1014.1SECTION 62.15855
   62.15855 Am I subject to this subpart
40:10.0.1.1.2.64.1014.2SECTION 62.15860
   62.15860 What SSI units are exempt from the federal plan
40:10.0.1.1.2.64.1014.3SECTION 62.15865
   62.15865 How do I determine if my SSI unit is covered by an approved and effective state or tribal plan
40:10.0.1.1.2.64.1014.4SECTION 62.15870
   62.15870 If my SSI unit is not listed on the federal plan inventory, am I exempt from this subpart
40:10.0.1.1.2.64.1015SUBJGRP 1015
Compliance Schedules
40:10.0.1.1.2.64.1015.5SECTION 62.15875
   62.15875 What is my final compliance date
40:10.0.1.1.2.64.1015.6SECTION 62.15880
   62.15880 [Reserved]
40:10.0.1.1.2.64.1015.7SECTION 62.15885
   62.15885 What must I include in the notifications of achievement of compliance
40:10.0.1.1.2.64.1015.8SECTION 62.15890
   62.15890 When must I submit the notifications of achievement of compliance
40:10.0.1.1.2.64.1015.9SECTION 62.15895
   62.15895 What if I do not meet the compliance date
40:10.0.1.1.2.64.1015.10SECTION 62.15900
   62.15900 How do I comply with the requirement for submittal of a control plan
40:10.0.1.1.2.64.1015.11SECTION 62.15905
   62.15905 How do I achieve final compliance
40:10.0.1.1.2.64.1015.12SECTION 62.15910
   62.15910 What must I do if I close my SSI unit and then restart it
40:10.0.1.1.2.64.1015.13SECTION 62.15915
   62.15915 What must I do if I plan to permanently close my SSI unit and not restart it
40:10.0.1.1.2.64.1016SUBJGRP 1016
Operator Training and Qualification
40:10.0.1.1.2.64.1016.14SECTION 62.15920
   62.15920 What are the operator training and qualification requirements
40:10.0.1.1.2.64.1016.15SECTION 62.15925
   62.15925 When must the operator training course be completed
40:10.0.1.1.2.64.1016.16SECTION 62.15930
   62.15930 How do I obtain my operator qualification
40:10.0.1.1.2.64.1016.17SECTION 62.15935
   62.15935 How do I maintain my operator qualification
40:10.0.1.1.2.64.1016.18SECTION 62.15940
   62.15940 How do I renew my lapsed operator qualification
40:10.0.1.1.2.64.1016.19SECTION 62.15945
   62.15945 What if all the qualified operators are temporarily not accessible
40:10.0.1.1.2.64.1016.20SECTION 62.15950
   62.15950 What site-specific documentation is required and how often must it be reviewed by qualified operators and plant personnel
40:10.0.1.1.2.64.1017SUBJGRP 1017
Emission Limits, Emission Standards and Operating Limits and Requirements
40:10.0.1.1.2.64.1017.21SECTION 62.15955
   62.15955 What emission limits and standards must I meet and by when
40:10.0.1.1.2.64.1017.22SECTION 62.15960
   62.15960 What operating limits and requirements must I meet and by when
40:10.0.1.1.2.64.1017.23SECTION 62.15965
   62.15965 How do I establish operating limits if I do not use a wet scrubber, fabric filter, electrostatic precipitator, activated carbon injection, or afterburner, or if I limit emissions in some other manner, to comply with the emission limits
40:10.0.1.1.2.64.1017.24SECTION 62.15970
   62.15970 Do the emission limits, emission standards, and operating limits apply during periods of startup, shutdown, and malfunction
40:10.0.1.1.2.64.1017.25SECTION 62.15975
   62.15975 [Reserved]
40:10.0.1.1.2.64.1018SUBJGRP 1018
Initial Compliance Requirements
40:10.0.1.1.2.64.1018.26SECTION 62.15980
   62.15980 How and when do I demonstrate initial compliance with the emission limits and standards
40:10.0.1.1.2.64.1018.27SECTION 62.15985
   62.15985 How do I establish my operating limits
40:10.0.1.1.2.64.1018.28SECTION 62.15990
   62.15990 By what date must I conduct the initial air pollution control device inspection and make any necessary repairs
40:10.0.1.1.2.64.1018.29SECTION 62.15995
   62.15995 How do I develop a site-specific monitoring plan for my continuous monitoring, bag leak detection, and ash handling systems, and by what date must I conduct an initial performance evaluation
40:10.0.1.1.2.64.1019SUBJGRP 1019
Continuous Compliance Requirements
40:10.0.1.1.2.64.1019.30SECTION 62.16000
   62.16000 How and when do I demonstrate continuous compliance with the emission limits and standards
40:10.0.1.1.2.64.1019.31SECTION 62.16005
   62.16005 How do I demonstrate continuous compliance with my operating limits
40:10.0.1.1.2.64.1019.32SECTION 62.16010
   62.16010 By what date must I conduct annual air pollution control device inspections and make any necessary repairs
40:10.0.1.1.2.64.1020SUBJGRP 1020
Performance Testing, Monitoring, and Calibration Requirements
40:10.0.1.1.2.64.1020.33SECTION 62.16015
   62.16015 What are the performance testing, monitoring, and calibration requirements for compliance with the emission limits and standards
40:10.0.1.1.2.64.1020.34SECTION 62.16020
   62.16020 What are the monitoring and calibration requirements for compliance with my operating limits
40:10.0.1.1.2.64.1021SUBJGRP 1021
Recordkeeping and Reporting
40:10.0.1.1.2.64.1021.35SECTION 62.16025
   62.16025 What records must I keep
40:10.0.1.1.2.64.1021.36SECTION 62.16030
   62.16030 What reports must I submit
40:10.0.1.1.2.64.1022SUBJGRP 1022
Title V - Operating Permits
40:10.0.1.1.2.64.1022.37SECTION 62.16035
   62.16035 Am I required to apply for and obtain a title V operating permit for my existing SSI unit
40:10.0.1.1.2.64.1022.38SECTION 62.16040
   62.16040 When must I submit a title V permit application for my existing SSI unit
40:10.0.1.1.2.64.1023SUBJGRP 1023
Definitions
40:10.0.1.1.2.64.1023.39SECTION 62.16045
   62.16045 What definitions must I know
40:10.0.1.1.2.64.1024SUBJGRP 1024
Delegation of Authority
40:10.0.1.1.2.64.1024.40SECTION 62.16050
   62.16050 What authorities will be retained by the EPA Administrator