Table 3 to Subpart GGG of Part 62—Generic Compliance Schedule and Increments of Progress
a
Increment
Date
Increment 1—Submit final control plan
1 year after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
Increment 2—Award Contracts
20 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
Increment 3—Begin on-site construction
24 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
Increment 4—Complete on-site construction
30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
Increment 5—Final compliance
30 months after initial NMOC emission rate report or the first annual emission rate report showing NMOC emissions ≥50 Mg/yr.b
a Table 3 of subpart GGG applies to landfills with design capacities ≥2.5 million megagrams and 2.5 million cubic meters that are subject to this subpart except those with site-specific compliance schedules shown in table 4 of subpart GGG.
b NMOC = nonmethane organic compounds Mg/yr = megagrams per year