Affected unitsIncrement 1

(submit final control plan)
Increment 2

(award contracts)
Increment 3

(begin onsite construction)
Increment 4

(complete onsite construction)
Increment 5

(final compliance)
1. All municipal waste combustors.a(Dates to be specified in state plan)(Dates to be specified in state plan)(Dates to be specified in state plan)(Dates to be specified in state plan)(Dates to be specified in state plan).b
a Plant specific schedules can be used at the discretion of the state.
b The date can be no later than 3 years after the effective date of state plan approval or March 10, 2031.