Appendix III to Part 1042 - Not-to-Exceed Zones
40:36.0.1.1.8.10.4.7.14 : Appendix III
Appendix III to Part 1042 - Not-to-Exceed Zones
(a) The following definitions apply for this Appendix III:
(1) Percent power means the percentage of the maximum
power achieved at Maximum Test Speed (or at Maximum Test Torque for
constant-speed engines).
(2) Percent speed means the percentage of Maximum Test
Speed.
(b) Figure 1 of this Appendix illustrates the default NTE zone
for marine engines certified using the duty cycle specified in §
1042.505(b)(1), except for variable-speed propulsion marine engines
used with controllable-pitch propellers or with electrically
coupled propellers, as follows:
(1) Subzone 1 is defined by the following boundaries:
(i) Percent power ÷ 100 > 0.7 · (percent speed ÷ 100)
2.5.
(ii) Percent power ÷ 100 ≤ (percent speed ÷ 90) 3.5.
(iii) Percent power ÷ 100 ≥ 3.0 · (1−percent speed ÷ 100).
(2) Subzone 2 is defined by the following boundaries:
(i) Percent power ÷ 100 ≥ 0.7 · (percent speed ÷ 100) 2.5.
(ii) Percent power ÷ 100 ≤ (percent speed ÷ 90) 3.5.
(iii) Percent power ÷ 100 < 3.0 · (1−percent speed ÷
100).
(iv) Percent speed ÷ 100 ≥ 0.7.
(3) Note that the line separating Subzone 1 and Subzone 2
includes the following endpoints:
(i) Percent speed = 78.9 percent; Percent power = 63.2
percent.
(ii) Percent speed = 84.6 percent; Percent power = 46.1
percent.
(c) Figure 2 of this Appendix illustrates the default NTE zone
for recreational marine engines certified using the duty cycle
specified in § 1042.505(b)(2), except for variable-speed marine
engines used with controllable-pitch propellers or with
electrically coupled propellers, as follows:
(1) Subzone 1 is defined by the following boundaries:
(i) Percent power ÷ 100 ≥ 0.7 · (percent speed ÷ 100) 2.5.
(ii) Percent power ÷ 100 ≤ (percent speed ÷ 90) 3.5.
(iii) Percent power ÷ 100 ≥ 3.0 · (1−percent speed ÷ 100).
(iv) Percent power ≤ 95 percent.
(2) Subzone 2 is defined by the following boundaries:
(i) Percent power ÷ 100 ≥ 0.7 · (percent speed ÷ 100) 2.5.
(ii) Percent power ÷ 100 ≤ (percent speed ÷ 90) 3.5.
(iii) Percent power ÷ 100 < 3.0 · (1−percent speed ÷
100).
(iv) Percent speed ≥ 70 percent.
(3) Subzone 3 is defined by the following boundaries:
(i) Percent power ÷ 100 ≤ (percent speed ÷ 90) 3.5.
(ii) Percent power > 95 percent.
(4) Note that the line separating Subzone 1 and Subzone 3
includes a point at Percent speed = 88.7 percent and Percent power
= 95.0 percent. See paragraph (b)(3) of this appendix regarding the
line separating Subzone 1 and Subzone 2.
(d) Figure 3 of this Appendix illustrates the default NTE zone
for variable-speed marine engines used with controllable-pitch
propellers or with electrically coupled propellers that are
certified using the duty cycle specified in § 1042.505(b)(1), (2),
or (3), as follows:
(1) Subzone 1 is defined by the following boundaries:
(i) Percent power ÷ 100 ≥ 0.7 · (percent speed ÷ 100) 2.5.
(ii) Percent power ÷ 100 ≥ 3.0 · (1−percent speed ÷ 100).
(iii) Percent speed ≥ 78.9 percent.
(2) Subzone 2a is defined by the following boundaries:
(i) Percent power ÷ 100 ≥ 0.7 · (percent speed ÷ 100) 2.5.
(ii) Percent speed ≥70 percent.
(iii) Percent speed <78.9 percent, for Percent power >63.3
percent.
(iv) Percent power ÷ 100 <3.0 · (1−percent speed ÷ 100), for
Percent speed ≥78.9 percent.
(3) Subzone 2b is defined by the following boundaries:
(i) The line formed by connecting the following two points on a
plot of speed-vs.-power:
(A) Percent speed = 70 percent; Percent power = 28.7
percent.
(B) Percent power = 40 percent; Speed = governed speed.
(ii) Percent power ÷ 100 < 0.7 · (percent speed ÷ 100)
2.5.
(4) Note that the line separating Subzone 1 and Subzone 2a
includes the following endpoints:
(i) Percent speed = 78.9 percent; Percent power = 63.3
percent.
(ii) Percent speed = 84.6 percent; Percent power = 46.1
percent.
(e) Figure 4 of this Appendix illustrates the default NTE zone
for constant-speed engines certified using a duty cycle specified
in § 1042.505(b)(3) or (4), as follows:
(1) Subzone 1 is defined by the following boundaries:
(i) Percent power ≥70 percent.
(ii) [Reserved]
(2) Subzone 2 is defined by the following boundaries:
(i) Percent power <70 percent.
(ii) Percent power ≥40 percent.
(f) Figure 5 of this Appendix illustrates the default NTE zone
for variable-speed auxiliary marine engines certified using the
duty cycle specified in § 1042.505(b)5)(ii) or (iii), as
follows:
(1) The default NTE zone is defined by the boundaries specified
in 40 CFR 86.1370(b)(1), (2), and (4).
(2) A special PM subzone is defined in 40 CFR 1039.515(b).
[81 FR
74157, Oct. 25, 2016]