Title 36
SECTION 51.57
51.57 How does a concessioner request arbitration of the construction cost of a capital improvement
§ 51.57 How does a concessioner request arbitration of the construction cost of a capital improvement?If a concessioner requests arbitration of the construction cost of a capital improvement determined by the Director, the request must be made in writing to the Director within 3 months of the date of the Director's determination of construction cost under § 51.56. The arbitration procedures are described in § 51.51. The decision of the arbitration panel as to the construction cost of the capital improvement will be binding on the concessioner and the Director.
[66 FR 35083, July 3, 2001]