§ 170.460 What must a project package include?

The project package must include the following documentation, approved by the appropriate Public Authority, before the start of construction:

(a) Plans, specifications, and estimates;

(b) A Tribal resolution or other authorized document supporting the project;

(c) Certification of compliance with the requirements of 25 CFR part 169, as well as any additional public taking documentation clearances, if applicable.

(d) Required environmental, archeological, and cultural clearances; and

(e) Identification of design exceptions if used in the plans.