192.711 Transmission lines: General requirements for repair procedures.

§ 192.711 Transmission lines: General requirements for repair procedures.

(a) Temporary repairs. Each operator must take immediate temporary measures to protect the public whenever:

(1) A leak, imperfection, or damage that impairs its serviceability is found in a segment of steel transmission line operating at or above 40 percent of the SMYS; and

(2) It is not feasible to make a permanent repair at the time of discovery.

(b) Permanent repairs. An operator must make permanent repairs on its pipeline system according to the following:

(1) Non integrity management repairs: The operator must make permanent repairs as soon as feasible.

(2) Integrity management repairs: When an operator discovers a condition on a pipeline covered under Subpart O-Gas Transmission Pipeline Integrity Management, the operator must remediate the condition as prescribed by § 192.933(d).

(c) Welded patch. Except as provided in § 192.717(b)(3), no operator may use a welded patch as a means of repair.