§ 62.15070 How do I comply with the increment of progress for awarding contracts?

40 CFR 62.15070

Citation40 CFR 62.15070
CorpusDaily eCFR
Displayed edition2026-06-23
Last updated2026-06-23

§ 62.15070 How do I comply with the increment of progress for awarding contracts?

You must submit a signed copy of the contracts awarded to initiate onsite construction, initiate onsite installation of emission control equipment, and incorporate process changes. Submit the copy of the contracts with the notification that this increment of progress has been achieved. You do not need to include documents incorporated by reference or the attachments to the contracts.