§ 62.14635a By what date must I conduct the initial air pollution control device inspection?

40 CFR 62.14635a

Citation40 CFR 62.14635a
CorpusDaily eCFR
Displayed edition2026-04-27
Last updated2026-04-27

§ 62.14635a By what date must I conduct the initial air pollution control device inspection?

(a) The initial air pollution control device inspection must be conducted within 60 days after installation of the control device and the associated CISWI reaches the charge rate at which it will operate, but no later than 180 days after January 10, 2025.

(b) Within 10 operating days following an air pollution control device inspection, all necessary repairs must be completed unless the owner or operator obtains written approval from the state agency establishing a date whereby all necessary repairs of the designated facility must be completed.