§ 60.5885 What happens to the operating requirements during periods of startup, shutdown, and malfunction?

40 CFR 60.5885

Citation40 CFR 60.5885
CorpusDaily eCFR
Displayed edition2026-05-14
Last updated2026-05-14

§ 60.5885 What happens to the operating requirements during periods of startup, shutdown, and malfunction?

The operating requirements under this subpart apply at all times including periods of municipal waste combustor warmup, startup, shutdown, and malfunction. Monitoring data cannot be dismissed or excluded from compliance calculations during periods of startup, shutdown, or malfunction, but must be recorded and reported in accordance with the provisions of § 60.6045(e). The provisions applicable to periods of startup, shutdown, and malfunction of § 60.8(c) of subpart A of this part do not apply.