Title 30

SECTION 585.816

585.816 What must I do if environmental or other conditions adversely affect a cable, pipeline, or facility

§ 585.816 What must I do if environmental or other conditions adversely affect a cable, pipeline, or facility?

If environmental or other conditions adversely affect a cable, pipeline, or facility so as to endanger the safety or the environment, you must:

(a) Submit a plan of corrective action to BOEM within 30 days of the discovery of the adverse effect.

(b) Take remedial action as described in your corrective action plan.

(c) Submit to the BOEM a report of the remedial action taken within 30 days after completion.