Title 30

SECTION 585.700

585.700 What reports must I submit to BOEM before installing facilities described in my approved SAP, COP, or GAP

§ 585.700 What reports must I submit to BOEM before installing facilities described in my approved SAP, COP, or GAP?

(a) You must submit the following reports to BOEM before installing facilities described in your approved COP (§ 585.632(a)) and, when required by this part, your SAP (§ 585.614(b)) or GAP (§ 585.651):

(1) A Facility Design Report; and

(2) A Fabrication and Installation Report.

(b) You may begin to fabricate and install the approved facilities after BOEM notifies you that it has received your reports and has no objections. If BOEM receives the reports, but does not respond with objections within 60 days of receipt or 60 days after we approve your SAP, COP, or GAP, if you submitted your report with the plan, BOEM is deemed not to have objections to the reports, and you may commence fabrication and installation of your facility or facilities.

(c) If BOEM has any objections, we will notify you verbally or in writing within 60 days of receipt of the report. Following initial notification of objections, BOEM may follow up with written correspondence outlining its specific objections to the report and request that certain actions be undertaken. You cannot commence activities addressed in such report until you resolve all objections to BOEM's satisfaction.