Title 30

SECTION 585.636

585.636 What notices must I provide BOEM following approval of my COP

§ 585.636 What notices must I provide BOEM following approval of my COP?

You must notify BOEM in writing of the following events, within the time periods provided:

(a) No later than 30 days after commencing activities associated with the placement of facilities on the lease area under a Fabrication and Installation Report.

(b) No later than 30 days after completion of construction and installation activities under a Fabrication and Installation Report.

(c) At least 7 days before commencing commercial operations.