585.618 What must I do upon completion of approved site assessment activities

§ 585.618 What must I do upon completion of approved site assessment activities?

(a) If, prior to the expiration of your site assessment term, you timely submit a COP meeting the requirements of this subpart, or a complete FERC license application, that describes the continued use of existing facilities approved in your SAP, you may keep such facilities in place on your lease during the time that BOEM reviews your COP for approval or FERC reviews your license application for approval.

(b) You are not required to initiate the decommissioning process for facilities that are authorized to remain in place under your approved COP or approved FERC license.

(c) If, following the technical and environmental review of your submitted COP, BOEM determines that such facilities may not remain in place, you must initiate the decommissioning process, as provided in subpart I of this part.

(d) If FERC determines that such facilities may not remain in place, you must initiate the decommissioning process as provided in subpart I of this part.

(e) You must initiate the decommissioning process, as set forth in subpart I of this part, upon the termination of your lease.