Subchapter K - Regulations Under The Public Utility Regulatory Policies Act Of 1978
18:1.0.1.11.58
PART 290
PART 290 - COLLECTION OF COST OF SERVICE INFORMATION UNDER SECTION 133 OF THE PUBLIC UTILITY REGULATORY POLICIES ACT OF 1978
18:1.0.1.11.58.1
SUBPART A
Subpart A - Coverage, Compliance and Definitions
18:1.0.1.11.58.1.28.1
SECTION 290.101
290.101 Applicability and exemptions.
18:1.0.1.11.58.1.28.2
SECTION 290.102
290.102 Information gathering and filing.
18:1.0.1.11.58.1.28.3
SECTION 290.103
290.103 Time of filing and reporting period.
18:1.0.1.11.58.1.28.4.8
APPENDIX Appendix A
Appendix A to Part 290 - Nonexempt Electric Utilities
18:1.0.1.11.59
PART 292
PART 292 - REGULATIONS UNDER SECTIONS 201 AND 210 OF THE PUBLIC UTILITY REGULATORY POLICIES ACT OF 1978 WITH REGARD TO SMALL POWER PRODUCTION AND COGENERATION
18:1.0.1.11.59.1
SUBPART A
Subpart A - General Provisions
18:1.0.1.11.59.1.28.1
SECTION 292.101
292.101 Definitions.
18:1.0.1.11.59.2
SUBPART B
Subpart B - Qualifying Cogeneration and Small Power Production Facilities
18:1.0.1.11.59.2.28.1
SECTION 292.201
292.201 Scope.
18:1.0.1.11.59.2.28.2
SECTION 292.202
292.202 Definitions.
18:1.0.1.11.59.2.28.3
SECTION 292.203
292.203 General requirements for qualification.
18:1.0.1.11.59.2.28.4
SECTION 292.204
292.204 Criteria for qualifying small power production facilities.
18:1.0.1.11.59.2.28.5
SECTION 292.205
292.205 Criteria for qualifying cogeneration facilities.
18:1.0.1.11.59.2.28.6
SECTION 292.207
292.207 Procedures for obtaining qualifying status.
18:1.0.1.11.59.2.28.7
SECTION 292.208
292.208 Special requirements for hydroelectric small power production facilities located at a new dam or diversion.
18:1.0.1.11.59.2.28.8
SECTION 292.209
292.209 Exceptions from requirements for hydroelectric small power production facilities located at a new dam or diversion.
18:1.0.1.11.59.2.28.9
SECTION 292.210
292.210 Petition alleging commitment of substantial monetary resources before October 16, 1986.
18:1.0.1.11.59.2.28.10
SECTION 292.211
292.211 Petition for initial determination on whether a project has a substantial adverse effect on the environment (AEE petition).
18:1.0.1.11.59.3
SUBPART C
Subpart C - Arrangements Between Electric Utilities and Qualifying Cogeneration and Small Power Production Facilities Under Section 210 of the Public Utility Regulatory Policies Act of 1978
18:1.0.1.11.59.3.28.1
SECTION 292.301
292.301 Scope.
18:1.0.1.11.59.3.28.2
SECTION 292.302
292.302 Availability of electric utility system cost data.
18:1.0.1.11.59.3.28.3
SECTION 292.303
292.303 Electric utility obligations under this subpart.
18:1.0.1.11.59.3.28.4
SECTION 292.304
292.304 Rates for purchases.
18:1.0.1.11.59.3.28.5
SECTION 292.305
292.305 Rates for sales.
18:1.0.1.11.59.3.28.6
SECTION 292.306
292.306 Interconnection costs.
18:1.0.1.11.59.3.28.7
SECTION 292.307
292.307 System emergencies.
18:1.0.1.11.59.3.28.8
SECTION 292.308
292.308 Standards for operating reliability.
18:1.0.1.11.59.3.28.9
SECTION 292.309
292.309 Termination of obligation to purchase from qualifying facilities.
18:1.0.1.11.59.3.28.10
SECTION 292.310
292.310 Procedures for utilities requesting termination of obligation to purchase from qualifying facilities.
18:1.0.1.11.59.3.28.11
SECTION 292.311
292.311 Reinstatement of obligation to purchase.
18:1.0.1.11.59.3.28.12
SECTION 292.312
292.312 Termination of obligation to sell to qualifying facilities.
18:1.0.1.11.59.3.28.13
SECTION 292.313
292.313 Reinstatement of obligation to sell.
18:1.0.1.11.59.3.28.14
SECTION 292.314
292.314 Existing rights and remedies.
18:1.0.1.11.59.4
SUBPART D
Subpart D - Implementation
18:1.0.1.11.59.4.28.1
SECTION 292.401
292.401 Implementation of certain reporting requirements.
18:1.0.1.11.59.4.28.2
SECTION 292.402
292.402 Waivers.
18:1.0.1.11.59.5
SUBPART E
Subpart E [Reserved]
18:1.0.1.11.59.6
SUBPART F
Subpart F - Exemption of Qualifying Small Power Production Facilities and Cogeneration Facilities from Certain Federal and State Laws and Regulations
18:1.0.1.11.59.6.28.1
SECTION 292.601
292.601 Exemption to qualifying facilities from the Federal Power Act.
18:1.0.1.11.59.6.28.2
SECTION 292.602
292.602 Exemption to qualifying facilities from the Public Utility Holding Company Act of 2005 and certain State laws and regulations.
18:1.0.1.11.60
PART 294
PART 294 - PROCEDURES FOR SHORTAGES OF ELECTRIC ENERGY AND CAPACITY UNDER SECTION 206 OF THE PUBLIC UTILITY REGULATORY POLICIES ACT OF 1978
18:1.0.1.11.60.0.28.1
SECTION 294.101
294.101 Shortages of electric energy and capacity.