Title 10 Part 719 → Subpart D → §719.31

Title 10 → Chapter III → Part 719 → Subpart D → §719.31

Electronic Code of Federal Regulations e-CFR

Title 10 Part 719 → Subpart D → §719.31

e-CFR data is current as of December 12, 2019

Title 10Chapter IIIPart 719Subpart D → §719.31


Title 10: Energy
PART 719—CONTRACTOR LEGAL MANAGEMENT REQUIREMENTS
Subpart D—Requests From Contractor Counsel To Initiate, Defend, and Settle Legal Matters


§719.31   When must the contractor initiate litigation against third parties?

The contractor must initiate litigation, upon the request of the contracting officer, against third parties including proceedings before administrative agencies, in connection with the contract. The contractor shall proceed with such litigation in good faith and as directed from time to time by Department Counsel.


© e-CFR 2019