Title 48

SECTION 2833.103

2833.103 Protests to the agency.

2833.103 Protests to the agency.

(a) The filing time frames in FAR 33.103(e) apply. An agency protest is filed when the protest complaint is received at the location the solicitation designates for serving protests.

(b) An interested party filing an agency protest has the choice of requesting either that the Contracting Officer or the Agency Protest Official decide the protest.

(c) In addition to the information required by FAR 33.103(d)(2), the protest must:

(1) Indicate that it is a protest to the agency.

(2) Be filed with the Contracting Officer.

(3) State whether the protestor chooses to have the Contracting Officer or the Agency Protest Official decide the protest. If the protest is silent on this matter, the Contracting Officer will decide the protest.

(4) Indicate whether the protestor prefers to make an oral or written presentation of arguments in support of the protest to the deciding official.

(d) The decision by the Agency Protest Official is an alternative to a decision by the Contracting Officer on a protest. The Agency Protest Official will not consider appeals from a Contracting Officer's decision on an agency protest.

(e) The deciding official must conduct a scheduling conference with the protestor within five (5) days after the protest is filed. The scheduling conference will establish deadlines for oral or written arguments in support of the agency protest and for agency officials to present information in response to the protest issues. The deciding official may hear oral arguments in support of the agency protest at the same time as the scheduling conference, depending on availability of the necessary parties.

(f) Oral conferences may take place either by telephone or in person. Other parties may attend at the discretion of the deciding official.

(g) The protestor has only one opportunity to support or explain the substance of its protest. Department of Justice procedures do not provide for any discovery. The deciding official has discretion to request additional information from either the agency or the protestor. However, the deciding official will normally decide protests on the basis of information provided by the protestor and the agency.

(h) The preferred practice is to resolve protests through informal oral discussion.

(i) An interested party may represent itself or be represented by legal counsel. The Department of Justice will not reimburse the protester for any legal fees related to the agency protest.

(j) If an agency protest is received before contract award, the Contracting Officer must not make award unless the Head of the Contracting Activity makes a determination to proceed under FAR 33.103(f)(1). Similarly, if an agency protest is filed within ten (10) days after award, the Contracting Officer must stay performance unless the Head of the Contracting Activity makes a determination to proceed under FAR 33.103(f)(3). Any stay of award or suspension of performance remains in effect until the protest is decided, dismissed, or withdrawn.

(k) The deciding official must make a best effort to issue a decision on the protest within twenty (20) days after the filing date. The decision may be oral or written. If oral, the deciding official must send a confirming letter within three (3) days after the decision using a means that provides receipt. The confirming letter must include the following information:

(1) State whether the protest was denied, sustained or dismissed.

(2) Indicate the date the decision was provided.

(l) If the deciding official sustains the protest, relief may consist of any of the following:

(1) Recommendation that the contract be terminated for convenience or cause.

(2) Recompeting the requirement.

(3) Amending the solicitation.

(4) Refraining from exercising contract options.

(5) Awarding a contract consistent with statute, regulation, and the terms of the solicitation.

(6) Other action that the deciding official determines is appropriate.

(m) If the Agency Protest Official sustains a protest, then within 30 days after receiving the Official's recommendations for relief, the Contracting Officer must either:

(1) Fully implement the recommended relief; or

(2) Notify the Agency Protest Official in writing of any recommendations have not been implemented and explain why.

(n) Proceedings on an agency protest may be dismissed or stayed if a protest on the same or similar basis is filed with a protest forum outside of the Department of Justice.