433.102 General.

433.102 General.

(a) The Senior Procurement Executive (SPE) is responsible for coordinating the handling of bid protests lodged with the Government Accountability Office (GAO).

(b) The head of the contracting activity (HCA), on a non-delegable basis, may resolve protests and authorize reimbursement of costs in accordance with FAR 33.102(b).

[61 FR 53646, Oct. 15, 1996, as amended at 70 FR 48, Jan. 3, 2005]