Title 48 Part 2448

Title 48 → Chapter 24 → Subchapter G → Part 2448

Electronic Code of Federal Regulations e-CFR

Title 48 Part 2448

e-CFR data is current as of July 19, 2018

Title 48Chapter 24Subchapter G → Part 2448


Title 48: Federal Acquisition Regulations System


PART 2448—VALUE ENGINEERING


Contents
2448.102   Policies.
2448.103   Processing value engineering change proposals.
2448.104-3   Sharing collateral savings.

Authority: 40 U.S.C. 486(c); 42 U.S.C. 3535(d).

Source: 71 FR 2437, Jan. 13, 2006, unless otherwise noted.

return arrow Back to Top

2448.102   Policies.

(a) The authority of the agency head to exempt contracts from including Value Engineering (VE) procedures and processes under 48 CFR 48.102(a) is delegated to the HCA for individual (case-by-case) exemptions and to the Senior Procurement Executive for class exemptions.

(b) The Senior Procurement Executive is responsible for managing and monitoring HUD's VE efforts.

return arrow Back to Top

2448.103   Processing value engineering change proposals.

Upon receipt of a Value Engineering Change Proposal (VECP), the Contracting Officer shall promptly forward it to the program office responsible for the contract, indicating:

(a) The date the VECP was received;

(b) The date by which the contractor must be informed of the government's acceptance or rejection of the VECP, unless additional time is required for evaluation;

(c) The date by which the Contracting Officer must know of the technical officer's decision in order to timely accept or reject the VECP;

(d) The need for information required to inform the contractor if the VECP is to be rejected or if additional time is needed to evaluate the VECP;

(e) The potential for awarding concurrent, future, or collateral savings to the contractor, if the VECP is accepted;

(f) That if the VECP is accepted, precise information will be needed with regard to the type of savings, and government costs, that can be expected from its acceptance;

(g) The need for a procurement request setting forth the specification changes to be used in a contract modification accepting the VECP in whole or in part; and

(h) The need for additional funds, if acceptance of the VECP will result in an increase in the cost of contract performance.

return arrow Back to Top

2448.104-3   Sharing collateral savings.

(a) The authority of the HCA to determine that the cost of calculating and tracking collateral savings will exceed the benefits to be derived under 48 CFR 48.104-3(a) is delegated to the Contracting Officer.

return arrow Back to Top