404.37 How will Reclamation determine the appropriate non-Federal share of construction costs

§ 404.37 How will Reclamation determine the appropriate non-Federal share of construction costs?

Reclamation will determine the appropriate non-Federal share of construction costs in the process of developing the feasibility report. The non-Federal cost-share will be:

(a) At least 25 percent of the total construction costs; and

(b) An additional amount based on your capability to pay, as appropriate, to be determined by Reclamation based on the factors in § 404.39.