471.14 What sanctions and penalties may be imposed for noncompliance, and what procedures will the Department follow in imposing such sanctions and penalties

§ 471.14 What sanctions and penalties may be imposed for noncompliance, and what procedures will the Department follow in imposing such sanctions and penalties?

(a) After a final decision on the merits has issued and before imposing the sanctions and penalties described in paragraph (d) of this section, the Director of OLMS will consult with the affected contracting agencies, and provide the heads of those agencies the opportunity to respond and provide written objections.

(b) If the contracting agency provides written objections, those objections must include a complete statement of reasons for the objections, which must include a finding that, as applicable, the completion of the contract, or further contracts or extensions or modifications of existing contracts, is essential to the agency's mission.

(c) The sanctions and penalties described in this section will not be imposed if:

(1) The head of the contracting agency, or his or her designee, continues to object to the imposition of such sanctions and penalties, or

(2) The contractor has not been given an opportunity for a hearing.

(d) In enforcing the Executive Order and this part, the Director of OLMS may take any of the following actions:

(1) Direct a contracting agency to cancel, terminate, suspend, or cause to be canceled, terminated or suspended, any contract or any portions thereof, for failure to comply with its contractual provisions required by Section 7(a) of the Executive Order and the regulations in this part. Contracts may be canceled, terminated, or suspended absolutely, or continuance of contracts may be conditioned upon compliance.

(2) Issue an order of debarment under Section 7(b) of the Executive Order providing that one or more contracting agencies must refrain from entering into further contracts, or extensions or other modification of existing contracts, with any non-complying contractor.

(3) Issue an order of debarment under Section 7(b) of the Executive Order providing that no contracting agency may enter into a contract with any non-complying subcontractor.

(e) Whenever the Director of OLMS exercises the authority in this section, the contracting agency must report the actions it has taken to the Director of OLMS within such time as the Director of OLMS will specify.

(f) Periodically, the Director of OLMS will publish and distribute to all executive agencies a list of the names of contractors and subcontractors that have, in the judgment of the Director of OLMS, failed to comply with the provisions of the Executive Order and this part, or of related rules, regulations, and orders of the Secretary of Labor, and as a result have been declared ineligible for future contracts under the Executive Order and the regulations in this part.