§ 245.415 Submission of materials to HUD: Timing of submission.

24 CFR 245.415

Citation24 CFR 245.415
CorpusDaily eCFR
Displayed edition2026-08-20
Last updated2026-08-20

§ 245.415 Submission of materials to HUD: Timing of submission.

(a) Initial submission. The mortgagor must submit the materials applicable to the covered action, as specified in §§ 245.416 through 245.419, to the local HUD office when the notice required under § 245.410 is served on the tenants.

(b) Subsequent submission. If additional notice under § 245.420(c) is required, the mortgagor must submit to HUD any changes to the materials required under §§ 245.416 through 245.419 when the notice required under § 245.420(c) is served on the tenants.