Title 7

SECTION 2500.048

2500.048 Review of disallowed costs.

§ 2500.048 Review of disallowed costs.

(a) Notice. If the OAO Project Officer (PO) determines that there is a basis for disallowing a cost, OAO shall provide the awardee written notice of its intent to disallow the cost. The written notice shall state the amount of the cost and the factual and legal basis for disallowing it.

(b) Awardee response. Within 60 days of receiving written notice of the PO's intent to disallow the cost, the awardee may respond with written evidence and arguments to show the cost is allowable, or that, for equitable, practical, or other reasons, shall not recover all or part of the amount, or that the recovery should be made in installments. An extension of time will be granted only in extenuating circumstances.

(c) Decision. Within 60 days of receiving the awardee's written response to the notice of intent to disallow the cost, the PO shall issue a management decision stating whether or not the cost has been disallowed, the reasons for the decision, and the method of appeal that has been provided under this section. If the awardee does not respond to the written notice under paragraph (a) of this section within the time frame specified in paragraph (b) of this section, the PO shall issue a management decision on the basis of the information available to it. The management decision shall constitute the final action with respect to whether the cost is allowed or disallowed. In the case of a questioned cost identified in the context of an audit subject to 7 CFR part 3052, the management decision will constitute the management decision under 7 CFR 3052.405(a).

(d) Demand for payment. If the management decision under paragraph (c) of this section constitutes a finding that the cost is disallowed and, therefore, that a debt is owed to the Government, the PO shall provide the required demand and notice pursuant to 7 CFR 3.11.

(e) Review process. Within 60 days of receiving the demand and notice referred to in paragraph (d) of this section, the awardee may submit a written request to the OAO Director for a review of the final management decision that the debt exists and the amount of the debt. Within 60 days of receiving the written request for a review, the OAO Director will issue a final decision regarding the debt. A review by the OAO Director or designee constitutes an administrative review for debts under 7 CFR part 3, subpart F.